Search Legislation

Wildlife Management and Muirburn (Scotland) Act 2024

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: Cross Heading: Making muirburn

 Help about opening options

Alternative versions:

Status:

This version of this cross heading contains provisions that are prospective. Help about Status

Close

Status

The term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section. A version of a provision is prospective either:

  1. where the provision (Part, Chapter or section) has never come into force or;
  2. where the text of the provision is subject to change, but no date has yet been appointed by the appropriate person or body for those changes to come into force.

Commencement Orders listed in the ‘Changes to Legislation’ box as not yet applied may bring this prospective version into force.

Changes to legislation:

There are currently no known outstanding effects for the Wildlife Management and Muirburn (Scotland) Act 2024, Cross Heading: Making muirburn. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Prospective

Making muirburnS

18Muirburn CodeS

(1)The Scottish Ministers must prepare a code (the “Muirburn Code”) in relation to how to make muirburn safely and appropriately.

(2)The Muirburn Code may, in particular, include provision as to—

(a)how the thickness of a layer of peat is to be determined,

(b)the times of day muirburn may be made,

(c)safety requirements when making muirburn.

(3)The Scottish Ministers must review and, if they consider it appropriate, revise the Muirburn Code by the end of each review period.

(4)The Scottish Ministers must publish the Muirburn Code prepared under subsection (1) and any revised code under subsection (3) as soon as practicable after it is prepared or, as the case may be, revised.

(5)The Scottish Ministers must, in preparing, reviewing or revising the Muirburn Code, consult—

(a)Scottish Natural Heritage, and

(b)such other persons as they consider likely to be interested in or affected by the making of muirburn including persons involved in the management of land on which muirburn may be made.

(6)Subsection (5)(a) does not apply during any period for which the functions under this section are delegated to Scottish Natural Heritage under section 21.

(7)In this section, “review period” means—

(a)the period of 5 years beginning with the day on which section 12 comes into force, and

(b)each subsequent period of 5 years.

Commencement Information

I1S. 18 not in force at Royal Assent, see s. 35(2)

19Notice of muirburn activityS

(1)A person who intends to make muirburn must give notice in writing under this section to—

(a)the owner of the proposed muirburn site (if different from the person making the muirburn), and

(b)any occupier of land situated within 1 kilometre of the proposed muirburn site.

(2)Notice need not be given to a person (“A”) under this section if A has given notice in writing to the person intending to make muirburn that A wishes not to be notified of any intention to make muirburn.

(3)Where there are 10 or more occupiers of land situated within 1 kilometre of the proposed muirburn site, the person intending to make muirburn may, instead of giving notice under subsection (1)(b) to each occupier separately, notify those occupiers collectively—

(a)by placing a notice in at least one newspaper circulating in the area which includes the proposed muirburn site, or

(b)by such other method as the Scottish Ministers may specify (whether in the Muirburn Code or otherwise) having regard to the need for the cost of giving notice to be reasonable to a person who intends to make muirburn.

(4)The Scottish Ministers must publicise any method for the time being specified (otherwise than in the Muirburn Code) for the purposes of subsection (3)(b).

(5)Notice under subsection (1) must—

(a)be given not less than 7 days before the muirburn is made,

(b)identify the proposed muirburn site (or sites),

(c)inform the person to whom notice is given (“A”) that A may require the person intending to make muirburn to provide further information in relation to—

(i)the dates on or between which the muirburn is intended to be made,

(ii)the proposed muirburn site (or sites), and

(iii)the approximate extent of the proposed muirburn.

(6)Where the owner of the proposed muirburn site or an occupier of land situated within 1 kilometre of the proposed muirburn site requests any of the further information mentioned in subsection (5)(c), the person intending to make the muirburn must make reasonable efforts to comply with the request no later than the end of the day before the muirburn is made.

(7)Any notice required to be given to an owner of land under this section may be given to any person purporting to be authorised by the owner to receive the notice.

(8)Any notice required to be given under this section may, as an alternative to being given by a method specified in section 26 of the Interpretation and Legislative Reform (Scotland) Act 2010, be given—

(a)by leaving it at an address to which it may be sent by virtue of subsection (2)(b) of that section, or

(b)where the identity of an occupier cannot, after reasonable inquiry, be ascertained by—

(i)addressing the notice to “Any occupiers of the land” (describing it), and

(ii)affixing it to some conspicuous object on the land.

Commencement Information

I2S. 19 not in force at Royal Assent, see s. 35(2)

20Muirburn seasonS

(1)For the purposes of this Part, the muirburn season is the period of time from 15 September in any year to 31 March in the following year.

(2)The Scottish Ministers may, by regulations, amend the dates in subsection (1) to extend or reduce the muirburn season.

(3)The Scottish Ministers may make regulations under subsection (2) only if they consider it necessary or expedient to do so—

(a)in relation to climate change, or

(b)for the purpose of—

(i)conserving, restoring, enhancing or managing the natural environment,

(ii)preventing, or reducing the risk of, wildfires causing harm to people or damage to property.

(4)The power under subsection (2) (by virtue of section 33) to make different provision for different purposes includes in particular power to make different provision for—

(a)different land (for example, land at different altitudes),

(b)different years.

(5)Before making regulations under subsection (2), the Scottish Ministers must consult—

(a)Scottish Natural Heritage, and

(b)such other persons as they consider likely to be interested in or affected by the making of muirburn, including persons involved in the management of land on which muirburn may be made.

(6)Regulations under subsection (2) are subject to the affirmative procedure.

Commencement Information

I3S. 20 not in force at Royal Assent, see s. 35(2)

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources