(1)Registration under section 10 of a controlled reservoir to which subsection (2) applies must take place before the end of the period of 6 months beginning with the relevant date.
(2)This subsection applies to controlled reservoirs which were, immediately before the relevant date, required to be registered in a large raised reservoirs register.
(3)In this section and sections 12, 13 and 16—
a “large raised reservoirs register” means a register maintained under section 2(2) of the 1975 Act,
“the relevant date” means the date of commencement of section 9.
Commencement Information
I1S. 11(1)(2) in force at 1.4.2015 by S.S.I. 2015/63, art. 2, Sch.
I2S. 11(3) in force at 1.1.2015 by S.S.I. 2014/348, art. 2, Sch.