Changes over time for: Cross Heading: Temporary stop notices

 Help about opening options

Changes to legislation:

Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997, Cross Heading: Temporary stop notices is up to date with all changes known to be in force on or before 10 June 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to the whole Act associated Parts and Chapters:

Whole provisions yet to be inserted into this Act (including any effects on those provisions):

[F1Temporary stop noticesS

Textual Amendments

F1Ss. 41A-41I and cross-headings inserted (30.6.2011 for specified purposes, 1.12.2011 in so far as not already in force) by Historic Environment (Amendment) (Scotland) Act 2011 (asp 3), ss. 23(1), 33(2); S.S.I. 2011/174, art. 2, sch.; S.S.I. 2011/372, art. 2, Sch.

41FTemporary stop noticesS

(1)Where it appears to the planning authority that—

(a)any works have been, or are being, executed to a listed building in their district,

(b)the works are such as to involve a contravention of section 8(1) or (2), and

(c)it is expedient that the works are (or any part of the works is) stopped immediately,

they may, if they consider it expedient to do so having regard to the effect of the works on the character of the building as one of special architectural or historic interest, issue a temporary stop notice.

(2)The notice must be given in writing and must—

(a)specify the works in question,

(b)prohibit execution of the works (or so much of the works as is specified in the notice), and

(c)set out the authority's reasons for issuing the notice.

(3)A temporary stop notice may be served on any of the following—

(a)a person who appears to the authority to be executing, or causing to be executed, the works,

(b)a person who appears to the authority to have an interest in the building (whether as owner or occupier or otherwise).

(4)The authority must display on the building—

(a)a copy of the notice, and

(b)a statement as to the effect of section 41H.

(5)A temporary stop notice has effect from the time a copy of it is first displayed in pursuance of subsection (4).

(6)A temporary stop notice ceases to have effect at the end of the period of 28 days starting on the day the copy notice is so displayed.

(7)But if a shorter period starting on that day is specified in the notice, the notice instead ceases to have effect at the end of that shorter period.

(8)And if the notice is withdrawn by the authority before that period of 28 days (or, as the case may be, that shorter period) expires, the notice ceases to have effect on being so withdrawn.

Modifications etc. (not altering text)

41GTemporary stop notices: restrictionsS

(1)A temporary stop notice does not prohibit the execution of works (either or both)—

(a)of such description,

(b)in such circumstances,

as may be prescribed.

(2)A second or subsequent temporary stop notice must not be issued in respect of the same works unless the planning authority have in the meantime taken some other enforcement action in relation to the contravention of section 8(1) or (2) which is constituted by the works.

(3)In subsection (2), “enforcement action” includes obtaining the grant of an interdict under section 146(2) of the principal Act (interdicts restraining breaches of planning control).

Modifications etc. (not altering text)

41HTemporary stop notices: offencesS

(1)A person who contravenes a temporary stop notice—

(a)which has been served on the person, or

(b)a copy of which has been displayed in pursuance of section 41F(4),

is guilty of an offence.

(2)Contravention of a temporary stop notice includes causing or permitting its contravention.

(3)An offence under this section may be charged by reference to a day or to a longer period of time.

(4)A person may, in relation to the same temporary stop notice, be convicted of more than one offence under this section by reference to different days or different periods.

(5)It is a defence in any proceedings under this section that—

(a)the temporary stop notice was not served on the accused, and

(b)the accused did not know, and could not reasonably have been expected to know, of its existence.

(6)A person convicted of an offence under this section is liable—

(a)on summary conviction, to a fine not exceeding £20,000,

(b)on conviction on indictment, to a fine.

(7)In determining the amount of the fine, the court is in particular to have regard to any financial benefit which has accrued or appears likely to accrue to the convicted person in consequence of the execution of the works which constituted the offence.

Modifications etc. (not altering text)

41ITemporary stop notices: compensationS

(1)A person who, at the date on which a temporary stop notice is first displayed in pursuance of section 41F(4), has an interest (whether as owner or occupier or otherwise) in the building to which the notice relates is entitled to be compensated by the planning authority in respect of any loss or damage directly attributable to the prohibition effected by that notice.

(2)But subsection (1) applies only if the circumstances are as set out in one or both of the following paragraphs—

(a)the works specified in the notice are authorised by listed building consent granted on or before the date mentioned in that subsection,

(b)the authority withdraws the notice other than following such grant of listed building consent as is mentioned in paragraph (a).

(3)Subsections (5) to (9) of section 41D apply to compensation payable under this section as they apply to compensation payable under that section; and for the purpose of that application the reference in section 41D(7) to a stop notice is to be taken to be a reference to a temporary stop notice.]

Modifications etc. (not altering text)

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill