Chwilio Deddfwriaeth

Water Act 2014

 Help about what version

Pa Fersiwn

 Help about advanced features

Nodweddion Uwch

 Help about opening options

Dewisiadau AgorExpand opening options

Changes over time for: Cross Heading: Sustainable drainage

 Help about opening options

Alternative versions:

Status:

Point in time view as at 15/12/2017.

Changes to legislation:

Water Act 2014, Cross Heading: Sustainable drainage is up to date with all changes known to be in force on or before 08 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Sustainable drainageE+W

21Drainage systems relieving public sewersE+W

(1)After section 114 of the Water Industry Act 1991 there is inserted—

Sustainable drainageE+W
114ADrainage systems relieving public sewers

(1)Sewerage undertakers may construct, on their own or on another's land, drainage systems for the purpose of reducing the volume of surface water entering public sewers or the rate at which it does so.

(2)A sewerage undertaker may maintain and operate a drainage system constructed by it under subsection (1).

(3)In this section—

  • drainage system” means a structure designed to receive rainwater and other surface water, other than a natural watercourse;

  • natural watercourse” means a river or stream;

  • rainwater” includes snow and other precipitation;

  • structure” includes—

    (a)

    any part of an existing or proposed structure, and

    (b)

    any feature or aspect of a design that is intended to receive or facilitate the receipt of rainwater or other surface water.

(4)The powers conferred by subsections (1) and (2) are not to be regarded as functions of a sewerage undertaker for the purposes of section 155 (compulsory purchase of land required for the purposes of carrying out functions of relevant undertakers).

(2)In section 158 of that Act (powers to lay pipes in streets), in subsection (7) (meaning of reference to a relevant pipe), in paragraph (b)—

(a)omit the “or” at the end of both sub-paragraphs (i) and (ii);

(b)after sub-paragraph (iii) there is inserted or

(iv)any pipe forming part of, or required in connection with, a drainage system constructed under section 114A.

(3)In Schedule 3 to the Flood and Water Management Act 2010 (sustainable drainage), after paragraph 19 there is inserted—

Exception 3: systems under section 114A Water Industry Act 1991

19AThe adoption duty does not apply to a drainage system constructed under section 114A of the Water Industry Act 1991 (drainage systems relieving public sewers).

Yn ôl i’r brig

Options/Help

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open y Ddeddf Gyfan

Y Ddeddf Gyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?