Article 2(1) and (3)

SCHEDULE 1SCHEDULED WORKS

Work No. 1An end-on connection between the Canal and the Board’s canal at Snarestone including a length of canal, stop lock and bywash. The length of the work is 70 metres commencing at grid reference point 434615E, 309970N, and terminating at 434656E, 310026N.
Work No. 2AA canal 497 metres in length commencing at the northern end of Work No. 1, grid reference point 434656E, 310026N, and terminating at Work No.3; an accommodation bridge at grid reference point 434775E, 310492N.
Work No. 2BA canal 586 metres in length commencing at Work No. 3; an accommodation bridge, at grid reference point 434770E, 310490N, and terminating at Work No. 4; an aqueduct over the Gilwiskaw Brook, at grid reference point 434926E, 311029N.
Work No. 2CA canal 713 metres in length commencing at Work No. 4; an aqueduct over the Gilwiskaw Brook, at grid reference point 434875E, 311117N, and terminating at Work No. 5; a highway bridge carrying B4116, Gallows Lane, at grid reference point 434356E, 311591N.
Work No. 2DA canal 230 metres in length commencing at Work No. 5; a highway bridge carrying B4116, Gallows Lane, commencing at grid reference point 434294E, 311623N, and terminating at Work No. 6; a footbridge, at grid reference point 434084E, 311612N.
Work No. 2EA canal 202 metres in length including a basin of area 0.56 hectares commencing at Work No. 6; a footbridge, at grid reference point 434080E, 311612N, and terminating at Work No. 7; a footbridge, at grid reference point 433959E and 311452N.
Work No. 2FA canal 656 metres in length commencing at Work No. 7; a footbridge, at grid reference point 433956E, 311446N, and terminating at Work No. 8, Horses Lane Bridge, at grid reference point 433555E, 311579N.
Work No. 2GA canal 291 metres in length commencing at Work No. 8, Horses Lane Bridge, grid reference point 433558E, 311569N, and terminating at Work No. 9; an accommodation bridge, at grid reference point 433296E, 311852N.
Work No. 2HA canal 81 metres in length commencing at Work No. 9; an accommodation bridge, commencing at grid reference point 433288E, 311859N, and terminating at Work No. 10; an aqueduct over High Street, Measham, at grid reference point 433224E, 311908N.
Work No. 2JA canal 771 metres in length commencing at Work No. 10; an aqueduct over High Street, Measham, commencing at grid reference point 433143E, 311966N, and terminating at Work No. 11; a footbridge, at grid reference point 433196E, 312201N.
Work No. 2KA canal 141 metres in length commencing at Work No. 11; a footbridge, commencing at grid reference point 433199E, 312196N, and terminating approximately 40m west of High Street, Measham, at grid reference point 433302E, 312100N.
Work No. 3An accommodation bridge at grid reference point 434775E, 310492N.
Work No. 4An aqueduct 102 metres in length to carry the canal over Gilwiskaw Brook commencing at grid reference point 434926E, 311029N, and terminating at grid reference point 434875E, 311117N.
Work No. 5A new highway bridge 70 metres in length to carry B 4116, Gallows Lane, over the canal south of its junction with Bosworth Road, commencing at grid reference point 434356E, 311591N, and terminating at grid reference point 434356E, 311591N.
Work No. 6A new footbridge 6 metres in length over the Canal between Measham Lodge Farm and Bosworth Road, to accommodate footpath P90 grid reference point 434084E, 311616N.
Work No. 7A new accommodation bridge 10 metres in length over the Canal 250m north west of Measham Lodge Farm, also serving footpath P85, at grid reference point 433959E, 311452N.
Work No. 8Alteration to the area of the existing three-arched Horses Lane Bridge at grid reference point 433558E, 311579N (arch 1 – raise ground level, arch 2 – construct central channel, arch 3 – excavate ground level to construct a towpath). The bridge is currently 90 metres in length and carries footpath P86.
Work No. 9New accommodation bridge 10 metres in length over the Canal, at grid reference point 433296E, 311852N.
Work No. 10An aqueduct 100 metres in length over High Street, Measham, at grid reference point 433224E, 311908N.
Work No. 11A footbridge 6 metres in length over the Canal, at grid reference point 433196E, 312201N.
Work No. 12Access track 190 metres in length off Bosworth Road, at grid reference point 434146E, 311689N.