Interpretation

54.—(1) The following provisions of this Part of this Schedule have effect unless otherwise agreed in writing between the Council and the Trust.

(2) In this Part of this Schedule—

“the Trust’s network” means the Trust’s network of waterways;

“construction”, in relation to any specified work or protective work, includes–

(a)

the execution and placing of that work; and

(b)

any relaying, renewal, or maintenance of that work as may be carried out during the period of 24 months from the completion of that work;

and “construct” and “constructed” have corresponding meanings;

“detriment” means any damage to the waterway or any other property of the Trust and, without limitation on the scope of that meaning, includes—

(c)

any obstruction of, or interference with, or hindrance or danger to, navigation or to any use of the waterway (including towing paths);

(d)

the erosion of the bed or banks of the waterway, or the impairment of the stability of any works, lands or premises forming part of the waterway;

(e)

the deposit of materials or the siltation of the waterway so as to damage the waterway;

(f)

the pollution of the waterway;

(g)

any significant alteration in the water level of the waterway, or significant interference with the supply of water to it, or drainage of water from it;

(h)

any harm to the ecology of the waterway (including any adverse impact on any site of special scientific interest comprised in the Trust’s network);

(i)

any interference with the exercise by any person of rights over the Trust’s network;

“the engineer” means an engineer appointed by the Trust for the purpose in question;

“plans” includes sections, designs, drawings, specifications, soil reports, calculations, descriptions (including descriptions of methods of construction) and programmes;

“practical completion” means practical completion of all of the specified work notwithstanding that items which would ordinarily be considered snagging items remain outstanding, and the expression “practically complete” and “practically completed” are to be construed accordingly;

“protective work” means a work constructed under paragraph 59(3)(a);

“specified work” means so much of any of the authorised works as is situated upon, across, under, over or within 15 metres of the waterway, or may in any way affect the waterway;

“towing path” means the towing path forming part of the waterway;

“the Trust” means the Canal & River Trust;

“the waterway” means the Grand Union Canal, and includes any works, lands or premises belonging to the Trust, or under its management or control, that are held or used by the Trust in connection with that canal.