The construction and operation of a nationally significant infrastructure project as defined in sections 14(1)(a) and 15 of the 2008 Act, comprising—
Work No. 1 – an onshore electricity generating station located on land at the Ferrybridge Power Station site, north-west of Knottingley, West Yorkshire, with a gross combined installed generating capacity of up to 90MWe, fuelled (subject to requirement 3) by waste derived fuels and comprised of the following works—
Work No. 1A – the generating station and its main process area, including—
fuel reception and storage facilities, consisting of a tipping hall and vehicle ramps, shredder, fuel storage bunker and crane;
a combustion system housed within a boiler hall comprising two combustion lines and associated boilers;
a steam turbine and generator housed within a turbine hall;
a bottom ash handling system, including storage bunker and ash collection bay;
a flue gas treatment system, including residue and reagent storage silos and tanks;
an emissions stack and associated emissions monitoring systems;
a cooling system comprising an air cooled condenser;
a compressed air system;
diesel storage tanks;
a process effluent storage tank;
a demineralised water treatment plant;
fire water tank and fire protection facilities;
up to two auxiliary diesel generators each of up to 4MWe output;
pipe racks and pipe runs;
an electrical switchyard, including circuit breaker and transformer;
a control and administrative building;
a workshop building; and
hardstandings, internal vehicular access roads, vehicle turning, waiting and parking areas and pedestrian and cycle facilities and routes.
Work No. 1B – in connection with and in addition to Work No. 1A, supporting buildings, works and areas, including—
a vehicular access road, level crossing and pedestrian and cycle facilities and routes;
security gatehouses and barriers;
up to four weighbridges;
a heavy goods vehicle holding area;
an external fuel container storage area;
vehicle parking;
an outage contractor compound; and
a surface water attenuation pond and surface water drainage connection and pipework to Fryston Beck.
Work No. 1C – in connection with and in addition to Work No. 1A, further supporting works, including a towns mains water connection and pipework to Stranglands Lane.
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys