Directive 2009/31/EC of the European Parliament and of the Council of 23 April 2009 on the geological storage of carbon dioxide and amending Council Directive 85/337/EEC, European Parliament and Council Directives 2000/60/EC, 2001/80/EC, 2004/35/EC, 2006/12/EC, 2008/1/EC and Regulation (EC) No 1013/2006 (Text with EEA relevance)
Print Options
PrintThe Whole
Directive
PrintThe Whole
Chapter
PrintThis
Article
only
Changes over time for: Article 20
Timeline of Changes
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Status:
EU Directives are published on this site to aid cross referencing from UK legislation. Since IP completion day (31 December 2020 11.00 p.m.) no amendments have been applied to this version.
Article 20U.K.Financial mechanism
1.Member States shall ensure that the operator, on the basis of arrangements to be decided by the Member States, makes a financial contribution available to the competent authority before the transfer of responsibility pursuant to Article 18 has taken place. The contribution from the operator shall take into account those criteria referred to in Annex I and elements relating to the history of storing CO2 relevant to determining the post-transfer obligations, and cover at least the anticipated cost of monitoring for a period of 30 years. This financial contribution may be used to cover the costs borne by the competent authority after the transfer of responsibility to ensure that the CO2 is completely and permanently contained in geological storage sites after the transfer of responsibility.
2.The Commission may adopt guidelines for the estimation of the costs referred to in paragraph 1 to be developed in consultation with Member States with a view to ensuring transparency and predictability for operators.