Commission Implementing Regulation (EU) 2015/2333 of 14 December 2015 amending Implementing Regulation (EU) No 809/2014 laying down rules for the application of Regulation (EU) No 1306/2013 of the European Parliament and of the Council with regard to the integrated administration and control system, rural development measures and cross compliance

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening Options

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Changes to legislation:

This version of this Regulation was derived from EUR-Lex on IP completion day (31 December 2020 11:00 p.m.). It has not been amended by the UK since then. Find out more about legislation originating from the EU as published on legislation.gov.uk. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Article 1U.K.Amendment of Implementing Regulation (EU) No 809/2014

Implementing Regulation (EU) No 809/2014 is amended as follows:

(1)

Article 10 is replaced by the following:

Article 10Advances for direct payments

Where a Member State pays advances for direct payments in accordance with Article 75 of Regulation (EU) No 1306/2013, the adjustment rate for financial discipline referred to in Article 8 of Regulation (EU) No 1307/2013 shall not be taken into account for calculating those advance payments.

The balance payment to be granted to beneficiaries as from 1 December shall take into account the adjustment rate for financial discipline applicable to the relevant claim year for the total amount of direct payments in relation to that year.

(2)

In Article 11, the following paragraphs 4 and 5 are added:

4.Where the integrated system provides for the pre-established form and the corresponding graphic material referred to in Article 72(3) of Regulation (EU) No 1306/2013 through a GIS-based interface, enabling the processing of the spatial and alphanumerical data of the areas declared (hereinafter referred to as “geo-spatial aid application form”), Member States may decide to introduce a system of preliminary cross-checks (hereinafter referred to as “preliminary checks”), which shall include at least the cross-checks referred to in points (a), (b) and (c) of the first subparagraph of Article 29(1) of this Regulation. The results shall be notified to the beneficiary within a period of 26 calendar days after the final date of submission of the single application, aid application or payment claims referred to in Article 13 of this Regulation. However, where this period of 26 calendar days expires before the final date for notification of amendments in accordance with Article 15(2) of this Regulation, the results shall be notified to the beneficiary at the latest the calendar day following the final date for notification of amendments of the year concerned.

Member States may decide to carry-out such preliminary checks at regional level, provided that the system using the geo-spatial aid application form is set up at regional level.

5.Where the beneficiary is a group of persons applying for support for agri-environment-climate operations as referred to in Article 28 of Regulation (EU) No 1305/2013 (hereinafter referred to as “collective”), the Member State may decide to derogate from the requirement in Article 14 of this Regulation that the payment claim is to contain all information necessary to establish eligibility for the support and from the restriction in Article 13 of this Regulation that all relevant data for the proper administrative and financial management of the support is to be submitted by the final date of submission of the payment claim, by introducing a simplified annual payment claim (hereinafter referred to as “collective claim”) that shall be submitted by a collective.

Articles 2, 3, 4, 9, 11, 13, 15 and 16, 17(1) and (3) to (9), and Articles, 21, 24, 25, 27, 28, 29, 35, 38, 39, 40, 42, 43 and 45 of this Regulation and Articles 4, 12 and 13 of Regulation (EU) No 640/2014 shall apply mutadis mutandis in respect of the particular requirements established in view of the collective claim.

For collectives, Member States shall include a description of the administrative arrangements in the rural development programme.

(3)

In Article 14, the following paragraph 4 is added:

4.For the purpose of the payment for agricultural practices beneficial for the climate and the environment in accordance with Chapter 3 of Title III of Regulation (EU) No 1307/2013, Member States may authorise the beneficiary to modify, in duly justified circumstances, the content of the single application as regards the use of the agricultural parcels, provided that this does not put the beneficiary in a more favourable position with regard to the fulfilment of the greening obligations based on the initial application. Member States may decide to set a final date for the notification of these modifications to the competent authority.

Where the competent authority has already informed the beneficiary of any case of non-compliance in the single application or payment claim or where it has given notice to the beneficiary of its intention to carry out an on-the-spot check or where an on-the-spot check reveals any non-compliance, modifications in accordance with the first subparagraph shall not be authorised in respect of the agricultural parcels affected by the non-compliance.

(4)

The following Article 14a is inserted:

Article 14aCollective claims

1.Where a Member State uses the option to introduce collective claims, Article 14 shall not apply in respect of such collective claims.

2.The collective shall submit one collective claim per year.

3.The collective claim shall contain all information necessary to establish eligibility for the support, with the exception of information in respect of the commitments covered by the agri-environment-climate operations as referred to in Article 28 of Regulation EU (No) 1305/2013. The collective claim shall contain in particular:

(a)the identity of the collective;

(b)the unique identification of each participating member of the collective;

(c)a reference to the application for support submitted by the collective;

(d)details of the agri-environment-climate operations concerned;

(e)particulars permitting the unambiguous identification of all agricultural parcels on the holding, their area expressed in hectares to two decimal places, their location and, where required, further specifications on the use of the agricultural parcels;

(f)where applicable, particulars permitting the unambiguous identification of non-agricultural land for which support under rural development measures is being claimed;

(g)where appropriate, any supporting documents needed to establish the eligibility for the measure concerned;

(h)a statement by the collective stating that the participating members are aware of the conditions pertaining to the rural development measures in question and of the financial consequences in cases of non-compliances.

Where the application for support submitted by the collective contains the information referred to in points (b), (d) and (h) of the first subparagraph, that information may be substituted by a reference to that application for support.

4.By way of derogation from the first subparagraph of paragraph 3, Member States may decide that the collective claim shall contain all details in respect of the commitments covered by the agri-environment-climate operations.

5.The collective shall notify the competent authority of each commitment covered by the agri-environment-climate operations no later than 14 calendar days before the commitment is undertaken. Member States shall provide for appropriate procedures for this notification.

Where the details in respect of the commitments covered by the agri-environment-climate operations are contained in the collective claim in accordance with paragraph 4, the commitments do not need to be notified in accordance with the first subparagraph of this paragraph, unless a change in type, timing or location of the commitment occurs.

(5)

Article 15 is amended as follows:

(a)

the title is replaced by the following:

(Article 15

Amendments to the single application or payment claim and modifications following the preliminary checks;

(b)

the following paragraph 1a is inserted:

1a.Where a beneficiary has been notified of the results of the preliminary checks as referred to in Article 11(4), that beneficiary may modify the single application or payment claim in order to include all necessary corrections with respect to individual parcels in accordance with the results of those cross-checks where they indicated a potential non-compliance.;

(c)

paragraph 2 is replaced by the following:

2.Amendments made in accordance with paragraph 1 shall be notified to the competent authority by 31 May of the year concerned, except in the case of Estonia, Latvia, Lithuania, Finland and Sweden, where they shall be notified by 15 June of the year concerned.

Such notifications shall be made in writing or via the geo-spatial aid application form.

By way of derogation from the first subparagraph, Member States may set an earlier final date for the notification of such amendments. That date shall however not be earlier than 15 calendar days after the final date for submitting the single application or payment claim fixed in accordance with Article 13(1).;

(d)

the following paragraph 2a is inserted:

2a.Modifications following the preliminary checks made in accordance with paragraph 1a shall be notified to the competent authority at the latest 35 calendar days after the final date of submission of the single application, aid application or payment claims referred to in Article 13. However, where this period of 35 calendar days expires before the final date for notification of amendments in accordance with paragraph 2 of this Article, the modifications shall be notified to the competent authority at the latest 10 calendar days after the final date for notification of amendments of the year concerned.

Such notifications shall be made in writing or via the geo-spatial aid application form.

(6)

In Article 17, paragraph 1 is replaced by the following:

1.For the purpose of the identification of all agricultural parcels on the holding and/or non-agricultural land as referred to in Article 14(1)(d) and (e), the competent authority shall provide the beneficiary with the geo-spatial aid application form.

(7)

In Article 25, the second subparagraph is replaced by the following:

However, for on-the-spot checks concerning livestock aid applications or payment claims under animal-related support measures or commitments notified in accordance with Article 14a(5), the announcement shall not exceed 48 hours, except in duly justified cases. Furthermore, where the legislation applicable to the acts and standards relevant to cross-compliance requires the on-the-spot check to be unannounced, those rules shall also apply in the case of on-the-spot checks related to cross-compliance.

(8)

In Article 26(2), the following second subparagraph is added:

The on-the-spot checks on commitments notified in accordance with Article 14a(5) shall be carried out within the time limits that ensure an effective verification of the commitment notified.

(9)

In Article 31, the first subparagraph of paragraph 3 is replaced by the following:

3.Where the ecological focus areas are not identified in the identification system for agricultural parcels as referred to in Article 70 of Regulation (EU) No 1306/2013, the control rate laid down in points (a) and (c) to (e) of paragraph 1 shall be supplemented by 5 % of all beneficiaries of the respective control population who are required to have ecological focus area on the agricultural area in accordance with Articles 43 and 46 of Regulation (EU) No 1307/2013.

(10)

Article 32 is amended as follows:

(a)

the following paragraph 2a is inserted:

2a.By way of derogation from paragraphs 1 and 2, where a Member State uses the option to introduce the collective claim, the control sample for on-the-spot checks carried out each year shall cover at least:

(a)5 % of all collectives submitting a collective claim; this sample shall, at the same time, cover at least 5 % of the total area declared in the collective claim in accordance with Article 14a(3); and

(b)5 % of the commitments notified in accordance with Article 14a(5).;

(b)

in paragraph 3, the following third subparagraph is added:

Where a Member State uses the option to introduce the collective claim, this paragraph shall not apply to collectives.

(11)

Article 34 is amended as follows:

(a)

paragraph 2 is amended as follows:

(i)

the first subparagraph is amended as follows:

  • in point (a), the following sentences are added:

    Beneficiaries selected randomly in accordance with the first subparagraph of paragraph 3 of this Article may be considered as part of the control sample provided for in the first sentence of this point. The number of such beneficiaries in the control sample shall not go beyond their proportion in the control population;;

  • the following point (ba) is inserted:

    (ba)between 0,6 % and 0,75 % of the control population as referred to in Article 31(1)(b) shall be selected randomly from all beneficiaries selected in accordance with point (a) of this subparagraph. Where necessary to reach that percentage, additional beneficiaries shall be selected randomly among the control population as referred to in Article 31(1)(b);;

  • point (c) is replaced by the following:

    (c)the remaining number of beneficiaries in the control sample referred to in Article 31(1)(a) and (b) shall be selected on the basis of a risk analysis;;

  • point (e) is replaced by the following:

    (e)all beneficiaries selected in accordance with points (a) to (d) of this subparagraph and those selected on the basis of a risk analysis in accordance with the first subparagraph of paragraph 3 of this Article may be considered as part of the control sample provided for in Article 30(a). Where necessary to respect the minimum control rate, additional beneficiaries shall be selected randomly from all beneficiaries applying for the basic payment scheme or the single area payment scheme in accordance with Chapter 1 of Title III of Regulation (EU) No 1307/2013;;

  • point (g) is deleted;

  • point (h) is replaced by the following:

    (h)between 20 % and 25 % of the minimum number of beneficiaries referred to in Article 31(1)(c) shall be selected randomly from all beneficiaries selected in accordance with point (a) of this subparagraph.. The remaining number of beneficiaries referred to in Article 31(1)(c) shall be selected on the basis of a risk analysis from all beneficiaries selected in accordance with point (e) of this subparagraph. Where necessary to respect the minimum control rates, additional beneficiaries shall be selected on the basis of a risk analysis from their respective control populations;;

  • the following point (ha) is inserted:

    (ha)between 20 % and 25 % of the minimum number of beneficiaries referred to in Article 31(1)(d) and (h) shall be selected randomly from all beneficiaries selected in accordance with point (b) of this subparagraph. Where necessary to reach that percentage, additional beneficiaries shall be selected randomly from all beneficiaries selected in accordance with point (a) of this subparagraph. The remaining number of beneficiaries referred to in Article 31(1)(d) and (h) shall be selected on the basis of a risk analysis from all beneficiaries selected in accordance with point (c) of this subparagraph. Where necessary to respect the minimum control rates, additional beneficiaries shall be selected on the basis of a risk analysis from their respective control populations;;

(ii)

the second and third subparagraphs are replaced by the following:

The on-the-spot check regarding the additional beneficiaries selected in accordance with points (d), (e), (h) and (ha) of the first subparagraph as well as the beneficiaries selected in accordance with point (f) of the first subparagraph may be limited to the aid scheme they have been selected for if the minimum control rates of the other aid schemes they applied for are already respected.

The on-the-spot check regarding the additional beneficiaries selected in accordance with Article 31(3) and the beneficiaries selected in accordance with points (h), (ha) and (i) of the first subparagraph of this paragraph may be limited to the greening practices they have been selected for if the minimum control rates of the other aid schemes and greening practices they are required to observe are already respected.;

(iii)

the following fifth subparagraph is added:

The additional beneficiaries to be subject to on-the-spot checks for the purposes of the first subparagraph of Article 31(3) shall be selected on the basis of a risk analysis.;

(b)

paragraph 3 is replaced by the following:

3.For the purposes of Articles 32 and 33, first between 20 % and 25 % of the minimum number of beneficiaries to be subject to on-the-spot checks and where Article 32(2a) is applied 100 % of the collectives and between 20 % and 25 % of the commitments to be subject to on-the-spot checks shall be selected randomly. The remaining number of beneficiaries and commitments to be subject to on-the-spot checks shall be selected on the basis of a risk analysis.

For the purposes of Articles 32 and 33, the random part of the sample may also include beneficiaries already selected in accordance with the first sentence of point (a) of the first subparagraph of paragraph 2 of this Article. The number of such beneficiaries in the control sample shall not go beyond their proportion in the control population.

For the purposes of Article 32, Member States may, as a result of the risk analysis, select specific rural development measures which apply to the beneficiaries.

(12)

Article 36 is amended as follows:

(a)

paragraph 2 is amended as follows:

(i)

the second and third subparagraphs are replaced by the following:

The first subparagraph shall only apply if a system of spatial intersection of all aid applications with the identification system for agricultural parcels is in place in accordance with Article 17(2) for all beneficiaries.

In respect of claim year 2015 the rate of errors found in the random sample checked on the spot shall not exceed 2 % in the preceding two financial years. That rate of errors shall be certified by the Member State in accordance with the established methodology drawn up at Union level.;

(ii)

the following fourth subparagraph is added:

In respect of claim year 2016 the rate of errors found in the random sample checked on the spot shall not exceed 2 % in the preceding financial year. That rate of errors shall be certified by the Member State in accordance with the new methodology drawn up at Union level taking account of Article 7(4) of Commission Implementing Regulation (EU) No 908/2014(1).;

(b)

in paragraph 3, the seventh subparagraph is replaced by the following:

The third and fourth subparagraphs of paragraph 2 shall apply mutatis mutandis.;

(c)

in paragraph 4, the second subparagraph is replaced by the following:

However, the first subparagraph shall not apply in relation to beneficiaries that include equivalent practices as referred to in Article 43(3) of Regulation (EU) No 1307/2013 and to collectives and commitments which are selected in accordance with Article 32(2a) of this Regulation.

(d)

in paragraph 5, the first sentence is replaced by the following:

Paragraphs 2, 3 and 4 shall only apply if the general conditions for reducing the minimum level of on-the-spot checks laid down in Article 41 of Implementing Regulation (EU) No 908/2014 are fulfilled.

(13)

In Article 37, the following paragraph 4 is added:

4.For collectives selected in accordance with point (a) of Article 32(2a), the on-the-spot checks shall cover the area measurement, verification of the eligibility criteria and other obligations of the area declared in the collective claim.

For commitments selected in accordance with point (b) of Article 32(2a), the on-the-spot check shall cover the verification of the commitments notified.

(14)

In Article 41(2), the following subparagraph is inserted after the first subparagraph:

By way of derogation from the first subparagraph, where the Member State uses the option to introduce collective claims, the Member State may decide not to give the collective the opportunity to sign the control report if no non-compliance is revealed during the check. If any non-compliance is revealed as a consequence of such checks, the opportunity to sign the report shall be given before the competent authority draws its conclusions from the findings with regard to any resulting reductions, refusals, withdrawals or penalties.

(15)

In the second subparagraph of Article 42(1), the following sentence is added:

However, where the retention period starts before an aid application or payment claim has been submitted or where it cannot be fixed in advance, Member States may decide that the on-the-spot checks provided for in Article 32 or 33 shall be spread over the period in which an animal may qualify for the payment or support.

(1)

Commission Implementing Regulation (EU) No 908/2014 of 6 August 2014 laying down rules for the application of Regulation (EU) No 1306/2013 of the European Parliament and of the Council with regard to paying agencies and other bodies, financial management, clearance of accounts, rules on checks, securities and transparency (OJ L 255, 28.8.2014, p. 59)’;

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources