Amendment of Schedule 1 (activities, installations and mobile plant)
This section has no associated Explanatory Memorandum
4. In Schedule 1, in Part C of section 1.1 (combustion activities), after head (a), insert—
“(b)Unless falling within head (a) of this Part, burning any fuel or fuels in a medium combustion plant with a net rated thermal input of 1 megawatt or more but less than a rated thermal input of 20 megawatts.
(c)Unless falling within another head in this part, the operation of a specified generator.”