1.—(1) An application to SEPA for a permit under regulation 7 shall be in writing (or in electronic form acceptable to it) and, subject to paragraphs 2 and 3, shall contain the following information:–
(a)the name of the applicant, his telephone number, address (including post code) and e-mail address (if any) and, if different, any address or e-mail address to which correspondence relating to the application should be sent and, if the applicant is a body corporate, its registered number, the address of its registered or principal office and, if that body corporate is a subsidiary of a holding company (within the meaning of section 736 of the Companies Act 1985()), the name of the ultimate holding company and the address of its registered or principal office;
(b)in the case of an application for a permit to operate an installation or Part A mobile plant, the address of the site of the installation or mobile plant and its national grid reference, a map or plan showing that site and, in the case of an installation, the location of the installation on that site, and the name of any local authority in whose area the site is situated;
(c)in the case of an application for a permit to operate a Part B mobile plant, the name of the local authority in whose area the applicant has his principal place of business and the address of that place of business or, where the operator of the mobile plant has his principal place of business outside of Scotland, the name of the local authority in whose area the plant was first operated or, where the plant has not been operated in Scotland, the local authority in whose area it is intended by the operator that the plant will first be operated;
(d)in the case of an application for a permit to operate a Part A installation or a Part A mobile plant, a site report containing the information required by sub-paragraph (2);
(e)a description of the installation or mobile plant, the activities listed in Part 1 of Schedule 1 to be carried out in the installation or by means of the mobile plant, and, in the case of an installation, any other directly associated activities to be carried out on the same site as the installation which will have a technical connection with those listed activities and which could have an effect on pollution;
(f)the raw and auxiliary materials and other substances and the energy to be used in or generated by the carrying out of the activities referred to in paragraph (e);
(g)the nature, quantities and sources of foreseeable emissions from the installation or mobile plant into each environmental medium, and a description of any foreseeable significant effects of the emissions on the environment;
(h)the proposed technology and other techniques for preventing or, where that is not practicable, reducing and rendering harmless emissions from the installation or mobile plant;
(i)the proposed measures to be taken to monitor the emissions;
(j)a description of the measures to be taken for the prevention and recovery of waste generated by the operation of the installation or mobile plant;
(k)a description of any proposed additional measures to be taken to comply with the general principles set out in regulation 8(2);
(l)in the case of an application for a permit to operate a Part A installation, any relevant information obtained or conclusion arrived at in relation to the installation pursuant to articles 5, 6 and 7 of Council Directive 85/337/EEC on the assessment of the effects of certain public and private projects on the environment();
(m)in the case of an application for a permit to operate an installation or mobile plant covered by general binding rules, a statement as to whether the applicant wishes the aspects of the operation of the installation or mobile plant covered by the requirements in the rules to be subject to those requirements instead of conditions included in the permit pursuant to regulation 9;
(n)in the case of an application for a permit that will authorise the carrying out of a specified waste management activity at an installation or by means of mobile plant, any information which the applicant wishes SEPA to take into account when considering whether the applicant is a fit and proper person to carry out that activity;
(o)any additional information which the applicant wishes SEPA to take into account in considering the application;
(p)a non-technical summary of the information referred to in the previous sub-paragraphs.
(2) The site report required by paragraph 1(d) shall describe the condition of the site of the installation or Part A mobile plant and shall, in particular, identify any substance in, on or under the land which may constitute a pollution risk.