- Latest available (Revised)
- Original (As enacted)
Local Government and Housing Act 1989, Paragraph 36 is up to date with all changes known to be in force on or before 19 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
36E+WThe following Schedule shall be inserted after Schedule 4—
1(1)If it comes to the notice of a charging authority that the work remaining to be done on a new building in its area is such that the building can reasonably be expected to be completed within 3 months, the authority shall serve a notice under this paragraph on the owner of the building as soon as is reasonably practicable unless the valuation officer otherwise directs in writing.
(2)If it comes to the notice of a charging authority that a new building in its area has been completed, the authority may serve a notice under this paragraph on the owner of the building unless the valuation officer otherwise directs in writing.
(3)A charging authority may withdraw a notice under this paragraph by serving on the owner of the building to which the notice relates a subsequent notice under this paragraph.
(4)Where an appeal under paragraph 4 below has been brought against a notice under this paragraph, the power conferred by sub-paragraph (3) above shall only be exercisable with the consent in writing of the owner of the building to which the notice relates.
(5)The power conferred by sub-paragraph (3) above shall cease to be exercisable in relation to a notice under this paragraph once a day has been determined under this Schedule as the completion day in relation to the building to which the notice relates.
(6)In this Schedule “completion notice” means a notice under this paragraph.
2(1)A completion notice shall specify the building to which it relates and state the day which the authority proposes as the completion day in relation to the building.
(2)Where at the time a completion notice is served it appears to the authority that the building to which the notice relates is not completed, the authority shall propose as the completion day such day, not later than 3 months from and including the day on which the notice is served, as the authority considers is a day by which the building can reasonably be expected to be completed.
(3)Where at the time a completion notice is served it appears to the authority that the building to which the notice relates is completed, the authority shall propose as the completion day the day on which the notice is served.
3(1)If the person on whom a completion notice is served agrees in writing with the authority by whom the notice is served that a day specified by the agreement shall be the completion day in relation to the building, that day shall be the completion day in relation to it.
(2)Where such an agreement as is mentioned in sub-paragraph (1) above is made, the completion notice relating to the building shall be deemed to have been withdrawn.
4(1)A person on whom a completion notice is served may appeal to a valuation and community charge tribunal against the notice on the ground that the building to which the notice relates has not been or, as the case may be, cannot reasonably be expected to be completed by the day stated in the notice.
(2)Where a person appeals against a completion notice and the appeal is not withdrawn or dismissed, the completion day shall be such day as the tribunal shall determine.
5Where a completion notice is not withdrawn and no appeal under paragraph 4 above is brought against the notice or any appeal under that paragraph is dismissed or withdrawn, the day stated in the notice shall be the completion day in relation to the building.
6(1)Where an appeal under paragraph 4 above is brought against a completion notice, then in relation to any day on which the appeal is pending section 45 above shall apply by virtue of section 46A(4) above as if the day stated in the notice had been determined under this Schedule as the completion day in relation to the building to which the notice relates.
(2)The Secretary of State may make regulations providing for the making of financial adjustments where sub-paragraph (1) applies but the day stated in the completion notice is not actually determined as the completion day in relation to the building to which the notice relates.
(3)Regulations under sub-paragraph (2) above may include—
(a)provision requiring payments to be made,
(b)provision requiring payments to be made together with payments of interest, and
(c)provision as to the recovery (by deduction or otherwise) of sums due.
(4)For the purpose of deciding, for the purposes of this paragraph, whether an appeal is pending on a particular day, the state of affairs existing immediately before the day ends shall be treated as having existed throughout the day.
7(1)A charging authority shall supply to the valuation officer a copy of any completion notice served by it.
(2)If a charging authority withdraws a completion notice, it shall inform the valuation officer of that fact.
(3)A charging authority shall supply the valuation officer with details of any agreement to which it is a party and by virtue of which a completion day is determined under this Schedule in relation to a building.
8Without prejudice to any other mode of service, a completion notice maybe served on a person—
(a)by sending it in a prepaid registered letter, or by the recorded delivery service, addressed to that person at his usual or last known place of abode or, in a case where an address for service has been given by that person, at that address;
(b)in the case of an incorporated company or body, by delivering it to the secretary or clerk of the company or body at their registered or principal office or sending it in a prepaid registered letter or by the recorded delivery service addressed to the secretary or clerk of the company or body at that office; or
(c)where the name or address of that person cannot be ascertained after reasonable inquiry, by addressing it to him by the description of “owner”of the building (describing it) to which the notice relates and by affixing it to some conspicuous part of the building.
9(1)This paragraph applies in the case of a building to which work remains to be done which is customarily done to a building of the type in question after the building has been substantially completed.
(2)It shall be assumed for the purposes of this Schedule that the building has been or can reasonably be expected to be completed at the end of such period beginning with the date of its completion apart from the work as is reasonably required for carrying out the work.
10(1)Section 46A(6) applies for the purposes of this Schedule.
(2)In this Schedule—
“completion notice” has the meaning given by paragraph 1(6) above;
“owner”, in relation to a building, means the person entitled to possession of the building;
references to the valuation officer, in relation to a charging authority, are references to the valuation officer for the authority.”
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: