Development by statutory undertakers

7.—(1) In Class 34 in Part 13 of Schedule 1 to the 1992 Order, in sub-paragraph (1) for the word “occupational” substitute the word “operational”.

(2) In Class 39 in Part 13 of Schedule 1 to the 1992 Order, for sub-paragraph (3)(c) substitute—

(c)in the case of any development referred to in sub-paragraph (1)(e)—

(i)the public gas supplier shall, before beginning the development, apply to the planning authority for a determination as to whether the prior approval of the authority will be required to the siting, design and external appearance of the building;

(ii)the application shall be accompanied by a written description of the proposed development and the materials to be used and a plan indicating the site together with any fee required to be paid;

(iii)the development shall not be begun before the occurrence of one of the following:—

(aa)the receipt by the applicant from the planning authority of a written notice of their determination that such prior approval is not required;

(bb)where the planning authority give the applicant notice within 28 days following the date of receiving his application of their determination that such prior approval is required, the giving of such approval;

(cc)the expiry of 28 days following the date on which the application was received by the planning authority without the planning authority making any determination as to whether such approval is required or notifying the applicant of their determination;

(iv)the development shall, except to the extent that the planning authority otherwise agree in writing, be carried out—

(aa)where prior approval is required, in accordance with the details approved;

(bb)where prior approval is not required, in accordance with the details submitted with the application;

(v)the development shall be carried out—

(aa)where approval has been given by the planning authority, within a period of five years from the date on which approval was given;

(bb)in any other case, within a perio d of five years from the date on which the planning authority were given the information referred to in sub-paragraph (c)(ii)..

(3) In Class 40 in Part 13 of Schedule 1 to the 1992 Order, for sub-paragraph (3)(d) substitute—

(d)in the case of any development referred to in sub-paragraph (1)(e)—

(i)the statutory undertaker shall, before beginning the development, apply to the planning authority for a determination as to whether the prior approval of the authority will be required to the siting, design and external appearance of the building;

(ii)the application shall be accompanied by a written description of the proposed development and the materials to be used and a plan indicating the site together with any fee required to be paid;

(iii)the development shall not be begun before the occurrence of one of the following:—

(aa)the receipt by the applicant from the planning authority of a written notice of their determination that such prior approval is not required;

(bb)where the planning authority give the applicant notice within 28 days following the date of receiving his application of their determination that such prior approval is required, the giving of such approval;

(cc)the expiry of 28 days following the date on which the application was received by the planning authority without the planning authority making any determination as to whether such approval is required or notifying the applicant of their determination;

(iv)the development shall, except to the extent that the planning authority otherwise agree in writing, be carried out—

(aa)where prior approval is required, in accordance with the details approved;

(bb)where prior approval is not required, in accordance with the details -submitted with the application;

(v)the development shall be carried out—

(aa)where approval has been given by the planning authority, within a period of five years from the date on which approval was given;

(bb)in any other case, within a period of five years from the date on which the planning authority were given the information referred to in sub-paragraph (d)(ii)..

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources