Search Legislation

The Construction (Design and Management) Regulations 2015

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: SCHEDULE 4

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for the The Construction (Design and Management) Regulations 2015, SCHEDULE 4. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Regulation 37

SCHEDULE 4U.K.Transitional and saving provisions

This schedule has no associated Explanatory Memorandum

1.  In this Schedule—U.K.

CDM co-ordinator” means a person appointed under regulation 14(1) of the 2007 Regulations;

competent” means competent to perform any requirement and avoid contravening any prohibition imposed on a person by or under any of the relevant statutory provisions;

relevant project” means a project which began before 6th April 2015.

2.  These Regulations apply to a relevant project with the modifications specified in this Schedule.U.K.

Projects with no existing CDM co-ordinator or principal contractorU.K.

3.—(1) This paragraph modifies the application of these Regulations in relation to a relevant project where, immediately before 6th April 2015—

(a)no CDM co-ordinator or principal contractor is appointed for the project under the 2007 Regulations;

(b)there is more than one contractor, or it is reasonably foreseeable that more than one contractor will be working on the project; and

(c)the construction phase has started.

(2) Regulation 5 does not apply to the project.

(3) The client may appoint in writing a designer as principal designer.

(4) The client must appoint in writing a contractor as principal contractor as soon as is practicable after 6th April 2015.

(5) The principal contractor must draw up a construction phase plan or make arrangements for a construction phase plan to be drawn up under regulation 12(1) and (2) as soon as is practicable after 6th April 2015 and the requirement that the plan must be drawn up during the pre-construction phase and before setting up a construction site is disapplied.

(6) The client, other than a domestic client, must ensure that the principal contractor complies with sub-paragraph (5) and the client duty in regulation 4(5)(a) is disapplied.

(7) If the client does not appoint a principal designer, the principal contractor must—

(a)prepare a health and safety file under regulation 12(5) as soon as is practicable after 6th April 2015 and the requirement for the file to be prepared during the pre-construction phase is disapplied; and

(b)ensure that the health and safety file is reviewed, updated and revised from time to time under regulation 12(6).

(8) If the client does not appoint a principal designer—

(a)the references to the principal designer in regulations 4(5)(b) and 9(3)(b) are treated as references to the principal contractor;

(b)the client duty in regulation 4(6)(a) does not apply; and

(c)the principal contractor duties in regulation 12(7) and 13(5) do not apply.

(9) Where a client, other than a domestic client, fails to appoint a principal contractor under sub-paragraph (4) the client must fulfil the duties of the principal contractor specified in these Regulations, as modified by this paragraph.

(10) Where the client is a domestic client—

(a)regulation 7(2) does not apply; and

(b)if the client fails to appoint a principal contractor under sub-paragraph (4) the principal contractor for the project is the contractor in control of the construction phase.

Projects with an existing CDM co-ordinatorU.K.

4.—(1) This paragraph and paragraphs 5 and 6 apply where, immediately before 6th April 2015, there is a CDM co-ordinator appointed for a relevant project.

(2) Where this paragraph applies, the appointment of the CDM co-ordinator continues to have effect for the purposes of these Regulations until a principal designer is appointed or the project comes to an end.

(3) The client must appoint in writing a principal designer for the project before 6th October 2015 unless the project comes to an end on or before that date.

(4) Where the appointment of a CDM co-ordinator continues to have effect under sub-paragraph (2)—

(a)the CDM co-ordinator must comply with the duties in paragraph 5;

(b)the duties in regulations 9(3)(b) and 12(7) to provide information to the principal designer are treated as duties to provide information to the CDM co-ordinator; and

(c)the duty in regulation 13(5) to liaise with the principal designer is treated as a duty to liaise with the CDM co-ordinator.

Duties of CDM co-ordinator during transitional periodU.K.

5.—(1) The CDM co-ordinator must—

(a)cooperate with any other person working on or in relation to a project at the same or an adjoining construction site, to the extent necessary to enable any person with a duty or function under these Regulations to fulfil that duty or function;

(b)where the CDM co-ordinator works under the control of another, report to that person anything they are aware of in relation to the project which is likely to endanger their own health or safety or that of others;

(c)ensure that suitable arrangements are made and implemented for the coordination of health and safety measures during the planning and preparation for the construction phase, including facilitating—

(i)cooperation and coordination between all persons working on the pre-construction phase of the project; and

(ii)the application of the general principles of prevention;

(d)liaise with the principal contractor over—

(i)the content of the health and safety file;

(ii)the information which the principal contractor needs to prepare the construction phase plan; and

(iii)any design development which may affect planning and management of the construction work;

(e)where no or partial pre-construction information has been supplied to the CDM co-ordinator by the client under regulation 10 of the 2007 Regulations, assist the client to comply with regulation 4(4) of these Regulations;

(f)unless the information has already been provided under regulation 20(2)(b) of the 2007 Regulations, provide any pre-construction information that is in the possession or control of the CDM co-ordinator, promptly and in a convenient form, to every designer and contractor appointed, or being considered for appointment, to the project;

(g)take all reasonable steps to ensure that designers comply with their duties under regulation 9 of these Regulations;

(h)take all reasonable steps to ensure cooperation between designers and the principal contractor during the construction phase in relation to any design or change to a design;

(i)if a health and safety file has not been prepared under regulation 20(2)(e) of the 2007 Regulations, prepare a health and safety file that complies with the requirements of regulation 12(5) of these Regulations;

(j)review, update and revise the health and safety file from time to time to take account of the work and any changes that have occurred;

(k)if the CDM co-ordinator's appointment continues to have effect immediately before the project ends, pass the health and safety file to the client at the end of the project;

(l)if a principal designer is appointed, pass the health and safety file and all other relevant health and safety information in the CDM co-ordinator's possession to the principal designer, as soon as is practicable after the appointment.

(2) The CDM co-ordinator must not arrange for or instruct a worker to carry out or manage design or construction work unless the worker is competent or under the supervision of a competent person.

Duties disapplied pending appointment of principal designerU.K.

6.—(1) The duties in regulation 5(1)(a) and (3) do not apply to a project referred to in paragraph 4(1).

(2) The following duties do not apply to a project referred to in paragraph 4(1) until the principal designer is appointed—

(a)the duties in regulation 4(5)(b) and (6)(a);

(b)the duties of the principal designer in regulations 11 and 12(3), (5), (6), (8) and (10).

(3) If a client fails to make the appointment required by paragraph 4(3) the client must fulfil the duties of a principal designer in regulations 11 and 12 on and after 6th October 2015.

Projects with only one contractorU.K.

7.  Where a relevant project has only one contractor and the construction phase has started, the contractor must draw up a construction phase plan, or make arrangements for a construction phase plan to be drawn up, under regulation 15(5) and (6) as soon as is practicable after 6th April 2015 and the requirement that the plan must be drawn up prior to setting up a construction site is disapplied.

SavingsU.K.

8.—(1) Where, immediately before 6th April 2015 there is a principal contractor appointed for a relevant project under regulation 14(2) of the 2007 Regulations, for the purposes of these Regulations that principal contractor is treated on and after 6th April 2015 as having been appointed under regulation 5(1)(b) of these Regulations.

(2) For the purposes of these Regulations, on and after 6th April 2015—

(a)a health and safety file prepared for a relevant project under regulation 20(2)(e) of the 2007 Regulations is treated as a health and safety file prepared under regulation 12(5) of these Regulations;

(b)a construction phase plan drawn up for a relevant project under regulation 23 of the 2007 Regulations is treated as a construction phase plan drawn up under regulation 12(1) or 15(5) of these Regulations;

(c)pre-construction information provided for a relevant project under regulation 10 of the 2007 Regulations is treated as pre-construction information provided under regulation 4(4) of these Regulations;

(d)notice given for a relevant project under regulation 21 of the 2007 Regulations is treated as notice given under regulation 6 of these Regulations.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources