The Building Safety Act 2022 (Commencement No. 4, Transitional and Saving Provisions) (Wales) Regulations 2024

 Help about what version

What Version

 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Transitional provision: higher-risk building work not commenced by 1 October 2024

8.  Where regulation 3(1) of these Regulations applies and higher-risk building work is not commenced before 1 October 2024, then—

(a)the initial notice related to the higher-risk building work will cease to be in force on 1 October 2024 for the purposes of section 47(4)(b)(ii) of the 1984 Act, and

(b)any plans certificate related to that initial notice will cease to be in force on 1 October 2024.