(1)Subject to the provisions of this section, every listed building consent shall be granted subject to the condition that the works to which it relates must be begun not later than the expiration of—
(a)five years beginning with the date on which the consent is granted; or
(b)such other period (whether longer or shorter) beginning with that date as the authority granting the consent may direct, being a period which the authority considers appropriate having regard to any material considerations.
(2)If listed building consent is granted without the condition required by subsection (1), it shall be deemed to have been granted subject to the condition that the works to which it relates must be begun not later than the expiration of five years beginning with the date of the grant.
(3)Nothing in this section applies to any consent to the retention of works granted under section 8(3).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: