SCHEDULE 17Protective provisions
Part 5Protection of F1Canal & River Trust
3
1
2
Any specified work shall not be constructed except in accordance with such plans as may be approved in writing by F2Canal & River Trust or determined under paragraph 11.
3
Any approval of F2Canal & River Trust required under this paragraph shall not be unreasonably withheld and—
a
shall be deemed to have been given if it is neither given nor refused (with an indication of the grounds for refusal) within 28 days of the submission of the plans for approval or where further particulars are submitted under paragraph 3(1), within 28 days of the submission of those particulars; and
b
may be given subject to such reasonable requirements as F2Canal & River Trust may make for the purpose of ensuring the safety or stability of the canal, including requirements as to the construction of protective works.
Words in Sch. 17 Pt. 5 heading substituted (2.7.2012) by The British Waterways Board (Transfer of Functions) Order 2012 (S.I. 2012/1659), art. 1(2), Sch. 3 para. 19(2) (with arts. 4-6)