153Transfer schemesU.K.

This section has no associated Explanatory Notes

(1)This section applies in relation to a scheme made by the Secretary of State under any of the following provisions (a “transfer scheme”)—

(a)Schedule 1;

(b)paragraph 16 of Schedule 2;

(c)Schedule 3;

(d)Schedule 11;

(e)Schedule 13.

(2)Subject to subsection (3), the Secretary of State may modify a transfer scheme.

(3)If a transfer under the scheme has taken effect, any modification under subsection (2) that relates to the transfer may be made only with the agreement of the person (or persons) affected by the modification.

(4)A modification takes effect from such date as the Secretary of State may specify; and that date may be the date when the original scheme came into effect.

(5)A transfer scheme may—

(a)include incidental, supplementary and consequential provision;

(b)make transitory or transitional provision or savings;

(c)make different provision for different cases or circumstances or for different purposes;

(d)make provision subject to exceptions.

(6)In the provisions mentioned in subsection (1), “subordinate legislation” means—

(a)subordinate legislation within the meaning of the Interpretation Act 1978 (see section 21(1) of that Act), or

(b)an instrument made under—

(i)an Act of the Scottish Parliament,

(ii)an Act or Measure of the National Assembly for Wales, or

(iii)Northern Ireland legislation.

Back to top

Options/Help

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?