This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 29/07/2021.
Changes to legislation:
Space Industry Act 2018, Section 48 is up to date with all changes known to be in force on or before 02 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
48Compensation in respect of planning decisions relating to spaceport safety etc: Northern IrelandN.I.
This section has no associated Explanatory Notes
(1)A district council in Northern Ireland is entitled to recover from the relevant person a sum equal to any compensation that council is liable to pay, if—
(a)the council becomes liable to pay compensation to any person because of a planning decision taken under the Planning Act (Northern Ireland) 2011 by a council, the Department for Infrastructure, or the Planning Appeals Commission, and
(b)the liability is attributable to a planning decision that would not have been taken but for the need to secure the safe and efficient operation of—
(i)a spaceport, or
(ii)range control apparatus.
(2)“The relevant person” is—
(a)where subsection (1)(b)(i) applies, the person authorised to operate the spaceport by a spaceport licence;
(b)where subsection (1)(b)(ii) applies, the range control service provider who operates the relevant range control apparatus.
(3)In this section—
“planning decision” includes a revocation or modification of a planning permission under Part 3 of the Planning Act (Northern Ireland) 2011;
“range control apparatus” means apparatus operated by a range control service provider for the purposes of providing range control services.