14.  Any dispute or difference between the undertaker and the Agency arising under, out of, or in connection with this article shall be referred to and settled by a single arbitrator appointed by agreement between the parties, on reference to him by either party, after notice in writing to the other, or, in default of agreement, by the President or Vice President of the Institution of Civil Engineers.