xmlns:atom="http://www.w3.org/2005/Atom"
6.—(1) Subject to the provisions of this article, for the purpose of carrying out and operating the scheduled works, the undertaker may, in connection with the construction of the authorised works, stop up any street specified in Schedule 5, to the extent specified in relation to that street in that Schedule.
(2) No street specified in columns (1) and (2) of Schedule 5 (being a street to be stopped up for which a substitute is to be provided by way of a diversion) shall be wholly or partly stopped up under this article until the new street to be substituted for it, which is described as a diversion in column (4) of that Schedule, has been completed to the reasonable satisfaction of the street authority and is open for use.
(3) Where a street has been stopped up under this article, all rights of way over or along the street so stopped up shall be extinguished.