- Latest available (Revised)
- Original (As made)
There are currently no known outstanding effects for the The Kentish Flats Extension Order 2013, Paragraph 1.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1.—(1) In this Schedule—E+W+S
“the 1990 Act” means the Town and Country Planning Act 1990(1);
“the 2008 Act” means the Planning Act 2008(2);
“the 2009 Act” means the Marine and Coastal Access Act 2009;
“authorised deposits” means the substances and articles specified in paragraph 2(4) of Part 1 of this Schedule;
“authorised development” means the development described in Part 1 of Schedule 1 to the Order;
“Cefas” means the Centre for Environment, Fisheries and Aquaculture Science or any replacement body or successor to its functions;
“the centre point of a wind turbine” means the centre point bisecting the turbine tower, transition piece and foundation;
“commence” means beginning to carry out any material operation (as defined in section 56(4) of the 1990 Act) forming part of the authorised development other than operations consisting of site clearance, demolition work, archaeological investigations, investigations for the purpose of assessing ground conditions, remedial work in respect of any contamination or other adverse ground conditions and “commencement” shall be construed accordingly;
“enforcement officer” means a marine enforcement officer within the meaning of section 235 of the 2009 Act;
“English Heritage” means the Historic Buildings and Monuments Commission for England or any successor to its statutory functions;
“the Environment Agency” means the body established under the Environment Act 1995(3) or any successor to its statutory functions;
“the environmental statement” means the document certified as the environmental statement by the Secretary of State for the purposes of the Order being application document reference number 4.1-4.3 dated October 2011;
“the Health and Safety Executive” or “HSE” means the body established under section 10 of the Health and Safety at Work etc. Act 1974(4) or any successor to its statutory functions or other authority performing, carrying out or having the same regulatory functions as the HSE has at the date of this licence;
“the intertidal area” means the area between mean high water level and mean low water level;
“the Kingfisher Fortnightly Bulletin” means the bulletin published by the Humber Seafood Institute or such other alternative publication approved in writing by the MMO for the purposes of this Schedule;
“the licence conditions” means the conditions set out in Part 2 of this Schedule;
“licensed activities” means the activities listed in Part 1 of this Schedule;
“the Marine Management Organisation” or “MMO” means the body of that name created under the Marine and Coastal Access Act 2009 or any successor to its functions;
“the Maritime and Coastguard Agency” or “MCA” means the executive agency of the Department for Transport or any successor to its functions;
“mean high water level” or “MHW” means the level of mean high water spring tides;
“mean low water level” or “MLW” means the level of mean low water spring tides;
“monopile foundation” means a metal pile, typically cylindrical, driven and/or drilled into the seabed and associated equipment;
“Natural England” means the body established by section 1 of the Natural Environment and Rural Communities Act 2006 or any successor to its statutory functions;
“notice to mariners” includes any notice to mariners which may be issued by the Admiralty, Trinity House, Queen’s harbourmasters, government departments and harbour and pilotage authorities;
“the Order” means the Kentish Flats Extension Order 2013;
“the Order limits” means the limits shown on the Order limits plan and works plan as the limits within which the authorised development may be carried out;
“the Order limits plan” means plan No 2.1 (Drawing no. 9V9546/30/001 rev. 004) certified as the Order limits plan by the Secretary of State for the purposes of the Order;
“PLA” means the Port of London Authority or any successor to its statutory functions;
“the project design statement” means the document certified as the project design statement by the Secretary of State for the purposes of the Order being document reference number 7.2 dated 10 October 2011;
“regulatory authorities” means any government department, public, local or regulatory or any other authority or institution having regulatory functions, powers, duties and obligations having the full force of law;
“the Requirements” means the requirements set out in paragraphs 2 to 18 of Part 3 of Schedule 1 to the Order;
“Trinity House” means the Corporation of Trinity House of Deptford Strond or any successor to its functions;
“the UK Hydrographic Office” means the Hydrographic Office of the Ministry of Defence, Taunton, Somerset TA1 2DN or any replacement body or successor to its functions;
“the undertaker” means, subject to article 7(3) of the Order, Vattenfall Wind Power Ltd;
“vessel” means every description of vessel, however propelled or moved, and includes a non-displacement craft, a personal watercraft, a seaplane on the surface of the water, a hydrofoil vessel, a hovercraft or any other amphibious vehicle and any other thing constructed or adapted for movement through, in, on or over water and which is at the time in, on or over water;
“VHF” means very high frequency; and
“wind turbine generator” or “wind turbine” means a structure comprising any or all of a tower, transition piece, rotor, blades, nacelle and ancillary electrical and other equipment which may include lighting, j-tubes, transition piece, access and rest platforms, access ladders, boat access systems, corrosion protection systems, fenders and maintenance equipment, fixed to a foundation;
“the works plan” means the plan No 5.4 (Drawing no. 9V9546/30/005 rev. 006) certified as the works plan by the Secretary of State for the purposes of the Order.
(2) In this Schedule references to the locations of a wind turbine are references to the centre point of that turbine.
(3) Except where otherwise notified in writing by the relevant organisation, the primary point of contact with the organisations listed below and the address for returns and correspondence shall be—
(a)Marine Management Organisation
Marine Environment Team
PO Box 1275
Newcastle upon Tyne
NE99 5BN
Tel: 0191 376 2525
(b)Marine Management Organisation
Coastal Office
Fish Market
Rock-A-Nore Road
Hastings
East Sussex
TN34 3DW
(c)Trinity House
Tower Hill
London
EC3N 4DH
Tel: 020 7481 6900
(d)The United Kingdom Hydrographic Office
Admiralty Way
Taunton
Somerset
TA1 2DN
Tel: 01823 337 900
(e)Maritime and Coastguard Agency
Navigation Safety Branch
Bay 2/04
Spring Place
105 Commercial Road
Southampton
SO15 1EG
Tel: 023 8032 9191
(f)Centre of Environment, Fisheries and Aquaculture Science
Pakefield Road
Lowestoft
Suffolk
NR33 0HT
Tel: 01502 562 244
(g)The Environment Agency
Orchard House
Endeavour Park
London Road
Addington
West Malling
Kent
ME19 5SH
Tel: 01732 223272
(h)Natural England
Hercules House
Hercules Road
Lambeth
London
SE1 7DU
Tel: 0300 060 4911
(i)English Heritage
Eastgate Court
195-205 High Street
Guildford
GU1 3EH
Tel: 01483 252 057
(j)Port of London Authority
London River House
Royal Pier Road
Gravesend
Kent
DA12 2BG
Tel 01474 562200
Commencement Information
I1Sch. 2 Pt. 1 para. 1 in force at 20.2.2013, see art. 1
1974 c. 37; section 10 of the Health and Safety at Work Act is substituted by S.I. 2008/960.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: