This Order authorises National Grid Electricity Transmission plc to uprate the overhead electricity line running from Waltham Cross substation to Tottenham substation from 275 kilovolts to 400 kilovolts including works to Waltham Cross substation, Brimsdown substation and Tottenham substation, and to carry out all associated works.

The Order permits National Grid Electricity Transmission plc to acquire compulsorily or by agreement, land and rights in land and to use land temporarily for this purpose.

The Order also makes provision in connection with the maintenance of the overhead electric line.

A copy of the plans, book of reference and other documents referred to in this Order and certified in accordance with article 43 of this Order may be inspected free of charge during working hours at the offices of National Grid Electricity Transmission PLC, 1-3 Strand, London WC2N 5EH.