[F1SCHEDULE 17U.K.CONFORMITY ASSESSMENT PROCEDURES

PART 1U.K.TYPE EXAMINATION (MODULE B)

1.(1) Type examination (Module B) is a conformity assessment procedure in which an approved body examines the technical design of an explosive and verifies and attests that the technical design of the explosive meets the requirements of these Regulations that apply to it.U.K.

(2) Type examination must be carried out as an assessment of the adequacy of the technical design of the explosive through—

(a)examination of the technical documentation and supporting evidence referred to in paragraph 2; and

(b)examination of a specimen of the production envisaged which is representative of the complete product (combination of production type and design type).

2.(1) A manufacturer must lodge an application for Type examination (Module B) with an approved body of the manufacturer's choice.U.K.

(2) The application must include—

(a)the name and address of the manufacturer and, if the application is lodged by the authorised representative, the name and address of the authorised representative;

(b)a written declaration that the same application has not been lodged with any other approved body;

(c)the technical documentation;

(d)the specimens representative of the production envisaged, and any further specimens requested by the approved body if needed for carrying out the test programme;

(e)the supporting evidence for the adequacy of the technical design solution; this supporting evidence must—

(i)mention any documents that have been used, in particular where the relevant designated standards have not been applied in full;

(ii)include, where necessary, the results of tests carried out in accordance with other relevant technical specifications by the appropriate laboratory of the manufacturer, or by another testing laboratory on the manufacturer's behalf and under the manufacturer's responsibility.

3.  The technical documentation referred to in paragraph 2(2)(c) must—U.K.

(a)make it possible to assess the explosive's conformity with the applicable requirements of these Regulations and must include an adequate analysis and assessment of any risks;

(b)specify the applicable requirements and cover, as far as relevant for the assessment, the design, manufacture and operation of the explosive;

(c)contain, wherever applicable, at least the following elements—

(i)a general description of the explosive;

(ii)conceptual design and manufacturing drawings and schemes of components, sub-assemblies and circuits;

(iii)descriptions and explanations necessary for the understanding of those drawings and schemes and the operation of the explosive;

(iv)a list of the designated standards applied in full or in part (where applicable specifying the parts which have been applied);

(v)where designated standards have not been applied, descriptions of the solutions adopted to meet the essential safety requirements, including a list of other relevant technical specifications applied to meet the essential safety requirements;

(vi)the results of design calculations made and examinations carried out;

(vii)test reports.

4.(1) The approved body must examine the technical documentation and supporting evidence in respect of an explosive to assess the adequacy of the technical design of the explosive.U.K.

(2) For each of the specimens examined, the approved body must—

(a)verify that the specimen—

(i)has been manufactured in conformity with the technical documentation;

(ii)identifies the elements which have been designed in accordance with the applicable provisions of the relevant designated standards, as well as the elements which have been designed in accordance with other relevant technical specifications;

(b)carry out appropriate examinations and tests, or have them carried out, to check whether, where the manufacturer has chosen to apply the solutions in the relevant designated standards, these have been applied correctly;

(c)carry out, or arrange the carrying out of, appropriate examinations and tests to check whether, where the solutions in the relevant designated standards have not been applied, the solutions adopted by the manufacturer applying other relevant technical specifications meet the corresponding essential safety requirements;

(d)agree with the manufacturer on a location where the examinations and tests will be carried out.

5.  The approved body must draw up an evaluation report that records the activities undertaken in accordance with paragraph 4 and their outcomes and, without prejudice to the approved body's obligations in relation to the Secretary of State, the approved body may disclose the content of that report, in full or in part, only with the agreement of the manufacturer.U.K.

6.(1) Where the type meets the applicable requirements of these Regulations, the approved body must issue a Type examination certificate to the manufacturer, which must contain—U.K.

(a)the name and address of the manufacturer;

(b)the conclusions of the examination;

(c)the conditions (if any) for its validity;

(d)the necessary data for the identification of the approved type;

(e)all relevant information to allow the conformity of manufactured explosives with the examined type to be evaluated and to allow for in-service control.

(2) The Type examination certificate referred to in sub-paragraph (1)—

(a)may have one or more annexes attached;

(b)must be accompanied by the descriptions and drawings necessary for identification of the approved type.

(3) Where the type does not satisfy the applicable requirements of these Regulations, the approved body must refuse to issue a Type examination certificate and must inform the applicant accordingly, giving detailed reasons for its refusal.

7.  An approved body must keep itself apprised of any changes in the generally acknowledged state of the art which indicate that the approved type may no longer comply with the applicable requirements of these Regulations, and must determine whether such changes require further investigation and, if so, the approved body must inform the manufacturer accordingly.U.K.

8.  A manufacturer must inform the approved body that holds the technical documentation relating to the Type examination certificate of all modifications to the approved type that may affect the conformity of the explosive with the essential safety requirements or the conditions for validity of that certificate; such modifications require additional approval in the form of an addition to the original Type examination certificate.U.K.

9.(1) Each approved body must inform the Secretary of State of all Type examination certificates and any additions thereto which it has issued or withdrawn, and must, periodically or upon request, make available to the Secretary of State the list of such certificates and any additions thereto refused, suspended or otherwise restricted.U.K.

(2) Each approved body must inform the other approved bodies of all Type examination certificates and any additions thereto which it has refused, withdrawn, suspended or otherwise restricted, and must, upon request, inform the other approved bodies of such certificates and additions thereto which it has issued.

(3) The other approved bodies and the Secretary of State may obtain from the approved body a copy of—

(a)the Type examination certificates and additions thereto;

(b)the technical documentation and the results of the examinations carried out by the approved body.

(4) An approved body must keep a copy of the Type examination certificate, its annexes and additions, as well as the file containing the technical documentation including the documentation submitted by the manufacturer, until the expiry of the validity of that certificate.

(5) A manufacturer must keep a copy of the Type examination certificate, its annexes and additions together with the technical documentation at the disposal of the relevant authorities for 10 years beginning on the day on which the explosive has been placed on the market.

10.  A manufacturer's authorised representative (if any) may lodge the application referred to in paragraph 2 and fulfil the obligations set out in paragraphs 8 and 9(5), provided that they are specified in the mandate by which they were appointed under regulation 46.]U.K.