The Central Bedfordshire Council (Woodside Link Houghton Regis) Development Consent Order 2014

Article 14

SCHEDULE 6PRIVATE ACCESSES TO AND FROM WORKS

(1)

Area

(2)

Description of access

District of Central BedfordshireAt point X1 on access plan 5 (being a point on Houghton Road, Chalton 130 metres north-east of the Chalton parish boundary), a temporary vehicular and pedestrian access to provide safe access and egress for site vehicles and plant and site workers’ personal vehicles to the construction compound to undertake all of the authorised development
At point X2 on access plan 2 (being a point on Parkside Drive, Houghton Regis 15 metres south of the junction with Fensome Drive), a temporary vehicular and pedestrian access to provide safe access and egress for site vehicles and plant to undertake the authorised development within Work Nos. 6 to 10 inclusive
At point X3 on access plan 1 (being a point on Sandringham Drive, Houghton Regis 80 metres east of the junction with Park Road North), a temporary vehicular and pedestrian access to provide safe access and egress for site vehicles and plant and site workers’ personal vehicles to undertake the authorised development within Work Nos. 1 to 6 inclusive
At point X7 on access plan 5 (being a point on the future M1 Junction 11A), a temporary vehicular access to provide safe access and egress for site vehicles and plant and site workers’ personal vehicles to undertake all of the authorised development
Borough of LutonAt point X4 on access plan 1 (being a point on Wheatfield Road, Luton 210 metres east of the junction with Poynters Road), a temporary vehicular and pedestrian access to provide safe access and egress for site vehicles and plant to undertake the authorised development within Work No. 5
At point X5 on access plan 2 (being a point on Pastures Way, Luton 2 metres south of the junction with Parkside Drive), a temporary vehicular and pedestrian access to provide safe access and egress for site vehicles and plant to undertake the authorised development within Work No. 10
At point X6 on access plan 3 (being a point at the eastern end of Kestrel Way, Luton), a temporary vehicular and pedestrian access to provide safe access and egress for site vehicles and plant to undertake the authorised development within Work No. 14