SCHEDULES

SCHEDULE 11REQUIREMENTS

Detailed design approval

5

Except where the authorised development is carried out in accordance with the drawings listed in paragraph 6, no authorised development may commence until details of the layout, scale and external appearance of the authorised development so far as they do not accord with the drawings listed in paragraph 6 have been submitted to and approved by the relevant planning authorities, and the authorised development must be carried out in accordance with the approved details.

6

The authorised development must be carried out in accordance with the drawings listed below, unless otherwise approved by the relevant planning authority in accordance with paragraph 5 and the altered development falls within the Order limits and has no significant environmental effects beyond those assessed in the environmental statement—

a

the application drawings, being those drawings with reference TR030001/APP/23a comprising—

i

drawing “AME-02006”;

ii

drawing “AME-02007”;

iii

drawing “AME-02008”;

iv

drawing “AME-02009”;

v

drawing “AME-02010”;

vi

drawing “AME-02011”;

vii

drawing “AME-02012”;

viii

drawing “AME-02013”;

ix

drawing “AME-02014”;

x

drawing “AME-02016”;

xi

drawing “AME-02017”; and

xii

drawing “AME-02018”;

b

the design drawings, being those drawings with reference TR030001/APP/23b comprising—

i

drawing “AMEP_P1D_D_001”;

ii

drawing “AMEP_P1D_D_002”;

iii

drawing “AMEP_P1D_D_005”;

iv

drawing “AMEP_P1D_D_006”;

v

drawing “AMEP_P1D_D_007”;

vi

drawing “AMEP_P1D_D_009”;

vii

drawing “AMEP_P1D_D_101”;

viii

drawing “AMEP_P1D_D_102”;

ix

drawing “AMEP_P1D_D_103”;

x

drawing “AMEP_P1D_D_104”;

xi

drawing “AMEP_P1D_D_105”;

xii

drawing “AMEP_P1D_D_106”; and

xiii

drawing “AMEP_P1D_D_107”; and

c

the sections, being those drawings with reference TR030001/APP/23b comprising—

i

drawing “AMEP_P1D_D_003”; and

ii

drawing “AMEP_P1D_D_004”.