xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULES

SCHEDULE 9PROTECTIVE PROVISIONS

PART 1FOR THE PROTECTION OF THE HUMBER CONSERVANCY

Removal of temporary works

11.  On completion of the construction of any part of a permanent authorised work, the Harbour Authority must as soon as practicable remove—

(a)any temporary tidal work carried out only for the purposes of that part of the permanent work; and

(b)any materials, plant and equipment used for such construction,

and must make good the site to the reasonable satisfaction of the Conservancy Authority.