Search Legislation

The Public Contracts Regulations 2015

Status:

This is the original version (as it was originally made).

Assessing suitability etc

This section has no associated Explanatory Memorandum

111.—(1) A contracting authority shall not include a pre-qualification stage in a procurement.

(2) Where the relevant threshold for the purposes of regulation 109(1) is that mentioned in regulation (5)(1)(a) or (d), paragraph (1) of this regulation applies only if the estimated value of the procurement is less than the lower threshold mentioned in paragraph (3).

(3) The lower threshold is the threshold mentioned in—

(a)regulation 5(1)(b) where the contracting authority is a central government authority;

(b)regulation 5(1)(c) where the contracting authority is a sub-central contracting authority.

(4) In paragraph (1), “pre-qualification stage” means a stage in the procurement process during which the contracting authority assesses the suitability of candidates to perform a public contract for the purpose of reducing the number of candidates to a smaller number who are to proceed to a later stage of the process.

(5) In any event, contracting authorities may ask candidates to answer suitability assessment questions only if each such question is—

(a)relevant to the subject-matter of the procurement; and

(b)proportionate.

(6) In paragraph (5), “suitability assessment question” means a question which relates to information or evidence which the contracting authority requires for the purpose of assessing whether candidates meet requirements or minimum standards of suitability, capability, legal status or financial standing.

(7) In complying with this regulation, contracting authorities shall have regard to any guidance issued by the Minister for the Cabinet Office, which may include guidance on how to establish and assess, without infringing paragraph (5), whether candidates meet requirements or minimum standards relating to suitability, capability, legal status and financial standing.

(8) Where a contracting authority conducts a procurement in a way which represents a reportable deviation from the guidance issued under paragraph (7), the contracting authority shall send to the Cabinet Office a report explaining the deviation.

(9) For that purpose, something is a reportable deviation only if it falls within criteria laid down for that purpose in guidance issued under paragraph (7).

(10) In this regulation, “candidate” means an economic operator that wishes to be considered for the award of a public contract.

Back to top

Options/Help

Print Options

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources