SCHEDULE 1Authorised development, ancillary and necessary works and Requirements
PART 3Requirements
Passive provision for western link32
1
No authorised development is to commence in respect of Work No. 6b until a scheme for safeguarding a future access to the Order land via the eastern bank of the River Tawe has been submitted to and approved by the relevant local planning authority.
2
The authorised development is to be carried out in accordance with the approved scheme.