SCHEDULE 1Authorised development, ancillary and necessary works and Requirements

PART 3Requirements

Passive provision for western link

32.—(1) No authorised development is to commence in respect of Work No. 6b until a scheme for safeguarding a future access to the Order land via the eastern bank of the River Tawe has been submitted to and approved by the relevant local planning authority.

(2) The authorised development is to be carried out in accordance with the approved scheme.