Passive provision for western link
32.—(1) No authorised development is to commence in respect of Work No. 6b until a scheme for safeguarding a future access to the Order land via the eastern bank of the River Tawe has been submitted to and approved by the relevant local planning authority.
(2) The authorised development is to be carried out in accordance with the approved scheme.