The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015

Detailed offshore design parameters

7.  Within Work No. 1B, the HVAC cables must not, in total,—

(a)exceed 1,270 kilometres in length;

(b)have cable protection (excluding cable crossings) exceeding 890,000 square metres in area;

(c)have cable protection (excluding cable crossings) exceeding 572,000 cubic metres in volume.