The Ferrybridge Multifuel 2 Power Station Order 2015

Commencement of the authorised development

1.—(1) The authorised development must commence within five years of the date on which this Order comes into force.

(2) The authorised development must not commence unless the undertaker has given the planning authority 14 days’ notice of its intention to commence the authorised development.