SCHEDULE 12Protective provisions

PART 5Protection of Environment Agency

8

1

Nothing in paragraphs 4(5), 5(3), 6 and 7(3) and (4) authorises the Agency to execute works on or affecting the authorised development without the prior consent in writing of the undertaker.

2

Consent under sub-paragraph (1) must not be unreasonably withheld or delayed, and the undertaker is deemed to have given its consent if it has not refused consent within 2 months of receiving a written request by the Agency.