SCHEDULE 2U.K.Essential Safety Requirements

PART 3U.K.MANUFACTURING

Final inspectionU.K.

26.—(1) Pressure equipment must undergo a final inspection to assess visually and by examination of the accompanying documents compliance with the requirements of these Regulations, for which purpose tests carried out during manufacture may be taken into account.

(2) So far as is necessary on safety grounds, the final inspection must be carried out internally and externally on every part of the equipment, where appropriate in the course of manufacture (for example where examination during the final inspection is no longer possible).