Stages of the development and design approval

3.—(1) No part of phase 2 is to commence until a written scheme setting out all the component parts of phase 2 has been submitted to and approved by the local planning authority. The written scheme must include details of the following unless they have been approved by the MMO under the provisions of Schedule 5 (deemed licence under the 2009 Act)—

(a)layout;

(b)details of additional quay structure and related infrastructure;

(c)external appearance and scale of all buildings and structures;

(d)parking and storage areas;

(e)surface and foul drainage;

(f)site levels;

(g)permanent fencing and other means of enclosure; and

(h)lighting.

(2) The phase 2 works must be carried out in accordance with the approved details, whether approved by the local planning authority under sub-paragraph (1) or the MMO under the provisions of Schedule 5.

(3) If the construction of works (a) (extension of quay) and (b) (dredging) comprised in phase 2 does not commence within 6 years of the completion of phase 1, if the local planning authority so requires, the undertaker must reassess the baseline conditions relating to those works and, in the event of there being changes to the baseline conditions which materially affect the assessment of likely impacts arising from those works identified in the environmental statement the undertaker must produce a further environmental report re-assessing such impacts, submit it to the local planning authority and agree with the local planning any additional mitigation measures required

(4) If a further environmental report is required, the works referred to in sub-paragraph (3) must not be carried out until either additional mitigation measures have been agreed with the local planning authority or it has been agreed with the local planning authority that no additional measures are required. Any additional mitigation measures required must be carried out as agreed.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources