9.—(1) No phase of the authorised development is to commence until written ecological management plans for any ecological mitigation or enhancement measures included in the environmental statement for that phase (including a marine mammal mitigation plan but not including the lagoon habitat enhancement works which are licensed under the DML), drafted in accordance with the principles set out in the outline ecological management plan, and incorporating the mitigation identified in the governance tracker have been submitted to and approved by the local planning authority and the MMO in consultation with Natural England and the Environment Agency.

(2) The ecological management plans must be implemented as approved but may be subject to amendment in accordance with article 37(2) (approvals pursuant to requirements etc.). If amendments to any ecological enhancement or mitigation measures are proposed below the level of high water, the amendments are to be approved by the local planning authority and the MMO in consultation with Natural England and the Environment Agency.

(3) Prior to the decommissioning phase of the authorised development, terrestrial ecological surveys are to be undertaken to verify whether any protected species could be impacted by the decommissioning phase, and to identify any requirement for mitigation to be implemented in order to avoid any adverse impacts. The scope of terrestrial ecological surveys is to be agreed with the local planning authority in consultation with Natural England prior to any ecological surveys being undertaken and, following the surveys, the scope of mitigation including an implementation timetable is to be agreed by the local planning authority in consultation with Natural England. The agreed mitigation must be carried out as agreed.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources