17.—(1) Prior to any works commencing below the level of high water, the undertaker must submit detailed method statements to the MMO for approval for each operation of the licensed activities at least 3 months prior to the commencement of such licensed activity and any such approval must not be unreasonably withheld or delayed and is deemed to have been permitted if it is neither given nor refused within 3 months of the specified day.
(2) The undertaker must provide the MMO with such further details as the MMO may reasonably require, any such request to be made within 28 days from the day on which the detailed method statement was submitted under sub-paragraph (1).
(3) In this paragraph the “specified day” means—
(a)the day on which the MMO have received the detailed method statement referred to in sub-paragraph (1); or
(b)the day on which the undertaker provides the MMO with such further particulars as have been reasonably requested by the MMO under sub-paragraph (2).
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: