- Latest available (Revised)
- Original (As made)
This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
10.—(1) Any authorised works within 100 metres of any apparatus or alternative apparatus capable of interfering with or risking damage to National Grid’s apparatus must not commence until a scheme for monitoring ground subsidence (referred to in this paragraph as “the monitoring scheme”) has been submitted to and approved by National Grid, such approval not to be unreasonably withheld or delayed.
(2) The ground subsidence monitoring scheme described in sub-paragraph (1) must set out—
(a)the apparatus which is to be subject to such monitoring;
(b)the extent of land to be monitored;
(c)the manner in which ground levels are to be monitored;
(d)the timescales of any monitoring activities; and
(e)the extent of ground subsidence which, if exceeded, would require the promoter to submit for National Grid’s approval a ground subsidence mitigation scheme in respect of such subsidence in accordance with sub-paragraph (3).
(3) The monitoring scheme required by sub-paragraphs (1) and (2) must be submitted at least 56 days prior to the commencement of any works authorised by this Order or comprised within the authorised development to which sub-paragraph (1) applies. Any requirements of National Grid must be notified within 28 days of receipt of the monitoring scheme. Thereafter the monitoring scheme must be implemented as approved, unless otherwise agreed in writing with National Grid.
(4) As soon as reasonably practicable after any ground subsidence identified by the monitoring activities set out in the monitoring scheme has exceeded the level described in sub-paragraph (2)(e), a scheme setting out necessary mitigation measures (if any) for such ground subsidence (referred to in this paragraph as a “mitigation scheme”) must be submitted to National Grid for approval, such approval not to be unreasonably withheld or delayed; and any mitigation scheme must be implemented as approved, unless otherwise agreed in writing with National Grid save that National Grid retains the right to carry out any further necessary protective works for the safeguarding of their apparatus and can recover any such costs in line with paragraph 8 (expenses).
(5) If the monitoring scheme or mitigation scheme would conflict with any aspect of any ground subsidence monitoring scheme or ground subsidence mitigation scheme approved by the local planning authority under Schedule 2 (requirements) the undertaker may submit a revised monitoring scheme or mitigation scheme to National Grid for its approval, such approval not to be unreasonably withheld or delayed; and the revised monitoring scheme or mitigation scheme must be implemented as approved, unless otherwise agreed in writing with National Grid.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: