Search Legislation

The York Potash Harbour Facilities Order 2016

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Costs

28.—(1) The undertaker must repay to owners of the protected land and operators of the pipelines all reasonable fees, costs, charges and expenses reasonably incurred by them in relation to these protective provisions in respect of—

(a)authorisation of survey details submitted by the undertaker under paragraph 3(3), authorisation of works details submitted by the undertaker under paragraph 4 and the imposition of conditions under paragraph 6;

(b)the engagement of an engineer and their observation of the authorised works affecting the pipelines and the provision of safety advice under paragraph 8;

(c)responding to the consultation on piling under paragraph 14;

(d)considering the effectiveness of any compacting which has taken place under paragraph 16, including considering and evaluating compacting testing results and the details of further compaction works under that paragraph;

(e)the repair and testing of a pipeline or protected crossing under paragraph 18;

(f)considering and responding to consultation in relation to the construction access plan under paragraph 21 and providing details of their programme for major works to the undertaker under paragraph 22;

(g)dealing with any request for consent or agreement by the undertaker under paragraph 25; and

(h)considering the adequacy of the terms and level of cover of any insurance policy proposed or put in place by the undertaker under paragraph 26,

including the reasonable costs incurred by owners and operators in engaging and retaining such external experts, consultants and contractors as may be reasonably necessary to allow the owner or operator to carry out its functions under these protective provisions.

(2) The undertaker must indemnify and keep the owners of the protected land and operators of the pipelines indemnified against all reasonable costs, charges, damages and expenses, and against consequential loss and damage, which may be occasioned or reasonably incurred by the owners and operators—

(a)by reason of the construction, operation, maintenance, repair and decommissioning of the authorised development or the failure of it; or

(b)by reason of any act or omission of the undertaker or of any person in its employ or of its contractors or others whilst engaged upon the construction, operation, maintenance, repair and decommissioning of the authorised development,

and the fact that any act or thing may have been done by the owner of protected land or operator of a pipeline on behalf of the undertaker or in accordance with plans approved by or on behalf of the owner or operator or in accordance with any requirement of the engineer appointed by the owner or operator or under his supervision does not (if it was done without negligence on the part of the owner or operator or of any person in their employ or of its contactors or agents) excuse the undertaker from any liability under the provisions of this sub-paragraph.

(3) An owner or operator must give the undertaker reasonable notice of any claim or demand under sub-paragraph (2) and no settlement or compromise of such a claim or demand is to be made without the prior consent of the undertaker.

(4) An owner or operator must, on receipt of a request from the undertaker, from time to time provide the undertaker free of charge with written estimates of the costs, charges, expenses and other liabilities for which the undertaker is or will become liable under this Schedule and with such information as may reasonably enable the undertaker to assess the reasonableness of any such estimate or claim made or to be made under this Schedule.

(5) In the assessment of any sums payable to an owner or operator under this Schedule there must not be taken into account any increase in the sums claimed that is attributable to any action taken by, or any agreement entered into by, the owner or operator if that action or agreement was not reasonably necessary and was taken or entered into with a view to obtaining the payment of those sums by the undertaker under this Schedule or increasing the sums so payable.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources