Requests for screening opinions of the relevant planning authority

This section has no associated Explanatory Memorandum

6.—(1) A person who is minded to carry out development may request the relevant planning authority to adopt a screening opinion.

(2) A person making a request for a screening opinion in relation to development where an application for planning permission has been or is proposed to be submitted must provide the following—

(a)a plan sufficient to identify the land;

(b)a description of the development, including in particular—

(i)a description of the physical characteristics of the development and, where relevant, of demolition works;

(ii)a description of the location of the development, with particular regard to the environmental sensitivity of geographical areas likely to be affected;

(c)a description of the aspects of the environment likely to be significantly affected by the development;

(d)to the extent the information is available, a description of any likely significant effects of the proposed development on the environment resulting from—

(i)the expected residues and emissions and the production of waste, where relevant; and

(ii)the use of natural resources, in particular soil, land, water and biodiversity; and

(e)such other information or representations as the person making the request may wish to provide or make, including any features of the proposed development or any measures envisaged to avoid or prevent what might otherwise have been significant adverse effects on the environment.

(3) A request for a screening opinion in relation to development where a subsequent application has been or is proposed to be submitted must be accompanied by—

(a)a plan sufficient to identify the land;

(b)sufficient information to enable the relevant planning authority to identify any planning permission granted for the development in respect of which a subsequent application has been made;

(c)the information described in paragraph (2)(c) and (d), but only to the extent that this relates to likely significant effects on the environment not previously identified; and

(d)such other information or representations as the person making the request may wish to provide or make, including any features of the proposed development or any measures envisaged to avoid or prevent what might otherwise have been significant adverse effects on the environment.

(4) A person compiling the information set out in paragraph (2) or (3) must, where relevant, take into account—

(a)the criteria set out in Schedule 3; and

(b)the results of any relevant EU environmental assessment which are reasonably available to the person requesting the screening opinion.

(5) A relevant planning authority receiving a request for a screening opinion must, if they consider that they have not been provided with sufficient information to adopt an opinion, notify in writing the person making the request of the points on which they require additional information.

(6) A relevant planning authority must adopt a screening opinion within—

(a)3 weeks beginning with the date of receipt of a request made pursuant to paragraph (1); or

(b)such longer period, not exceeding 90 days from the date on which the person making the request submits the information required under paragraph (2) or (3) as may be agreed in writing with the person making the request.

(7) Where the relevant planning authority considers that due to exceptional circumstances relating to the circumstances of the proposed development that it is not practicable for it to adopt a screening opinion within the relevant period specified in paragraph (6), the relevant planning authority may extend that period by notice in writing given to the person who made the request for a screening opinion.

(8) The relevant planning authority must state in any notice given under paragraph (7) the reasons justifying the extension of time and the date when the determination is expected.

(9) A relevant planning authority which adopts a screening opinion pursuant to paragraph (6) must send a copy to the person who made the request.

(10) Where a relevant planning authority—

(a)fails to adopt a screening opinion within the relevant period mentioned in paragraph (6); or

(b)adopts an opinion to the effect that the development is EIA development,

the person who requested the opinion may request the Secretary of State to make a screening direction.

(11) A person may make a request pursuant to paragraph (10) even if the relevant planning authority has not received the additional information which it has sought under paragraph (5).

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources