The National Grid (Richborough Connection Project) Development Consent Order 2017

Compulsory acquisition of right: incorporation of the mineral code

19.  Parts 2 and 3 of Schedule 2 to the Acquisition of Land Act 1981(1) (minerals) are incorporated into this Order subject to the modifications that—

(a)paragraph 8(3) is not incorporated; and

(b)for “the acquiring authority” there is substituted “the undertaker”.

(1)

1981 c. 67. Sub-paragraph (5) of paragraph 1 of Part 1 of Schedule 2 was amended by section 67 of, and paragraph 27(3) of Schedule 9 to, the Coal Industry Act 1994 (c. 21) and paragraph 8 of Part 3 of that Schedule 2 was amended by section 46 of the Criminal Justice Act 1982 (c. 48). There are other amendments to this Act which are not relevant to this Order.