SCHEDULE 1Authorised project

PART 3Requirements

Contaminated land and ground water19

1

Work No. 41 must not commence until a written scheme applicable to that work, to mitigate the potential for release of contaminants within the Order limits has, after consultation with the Environment Agency, been submitted to and approved by the relevant planning authority.

2

The written scheme referred to in paragraph (1) must be implemented as approved.