8.—(1) No part of the authorised development may be commenced until a Construction Traffic Management Plan for that part has been submitted to and approved by the relevant planning authority in consultation with the highway authority.
(2) The Construction Traffic Management Plan must:
(a)specify measures to mitigate the impacts of construction traffic during the construction works;
(b)be substantially in accordance with section 4.8 of the environmental statement; and
(c)include a travel plan for contractors that sets out measures to control the arrival and departure of construction staff during peak travel times (08:00 to 09:00 and 17:00 to 18:00 on weekdays).
(3) Construction works for the authorised development must be carried out in accordance with the approved Construction Traffic Management Plan for that part.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: