The Drax Power (Generating Stations) Order 2019

E+W

Work No. 7 – a gas pipeline including—

(a)Work No. 7A—

(i)an underground gas pipeline connection and telemetry cabling, 3km in length and up to 600 millimetres nominal diameter, connecting Work No. 5 to Work No. 6B;

(ii)pipeline field marker posts and cathodic protection test/transformer rectifier units;

(iii)below ground drainage works;

(iv)works required in order to protect existing utilities infrastructure;

(v)tree and hedge removal; and

(vi)hard and soft landscaping including tree planting, ecological mitigation, temporary and permanent fencing and other boundary treatments.

(b)Work No. 7B – temporary construction laydown area for gas pipeline.

Commencement Information

I1Sch. 1 in force at 25.10.2019, see art. 1