xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"
Article 2
Commencement Information
I1Sch. 13 Pt. 1 in force at 25.10.2019, see art. 1
Component | Work No. | Maximum length (m) | Maximum width (m) | Maximum height (m AGL) | Maximum height (m AOD) |
---|---|---|---|---|---|
Pedestrian Bridge | 9A(iii) | 33 | 10 | 11.5 | 17 |
Commencement Information
I2Sch. 13 Pt. 2 in force at 25.10.2019, see art. 1
Component | Work No. | Maximum length (m) | Maximum width (m) | Maximum height (m AGL) | Maximum height (m AOD) |
---|---|---|---|---|---|
Turbine hall building | 1A(ii) | 87 | 23 | 28 | 34 |
Heat recovery steam generator building (up to two) | 1A(iv) | 55 | 29 | 49 | 55 |
Exhaust gas emission flue stacks (up to two) | 1A(iv) | – | – | 123 | 129 |
Bypass stack (up to two) (excluding supporting structures) | 1A(v) | – | – | 123 | 129 |
Transformers | 1A(vi) | 36 | 20 | 11 | 17 |
Gas turbine air inlet filter house | 1A(vii) | 26 | 27 | 35 | 41 |
Power control centre | 1A(viii) | 17 | 17 | 6 | 12 |
Turbine outage store building (up to two) | 1A(xiv) | 113 | 43 | 28 | 34 |
Fuel gas station (up to two) | 1A(xvi) | 26 | 19 | 7 | 13 |
Main pipe rack | 1B(i) | 600 | 12 | 25 | 31 |
Battery storage facility including any structure (where constructed in its entirety in a single stage being stage 1) | 3A | 180 | 60 | 10 | 16 |
Battery storage facility including any structure (where constructed in two stages being stage 1 and stage 2) | 3A | 90 | 60 | 10 | 16 |
Gas insulated switchgear banking building | 4A | 18 | 12 | 11 | 17 |
Control room building for gas insulated switchgear | 4A | 26 | 12 | 11 | 17 |
Gas receiving facility (GRF) Compound | 5 | 85 | 85 | 10 | 16 |
Pig Trap Facility (Launching) Compound | 6B | 30 | 30 | 5 | 10 |
Minimum Offtake Connection | 6A | 30 | 30 | 5 | 10 |
Reinstatement of sludge lagoon | 12A | 82 | 55 | – | – |
Component | Work No. | Minimum height (m AGL) | Minimum height (m AOD) |
---|---|---|---|
Exhaust gas emission flue stacks (up to two) | 1A(iv) | 122.5 | 128.5 |
Bypass Stack (up to two) (excluding supporting structures) | 1A(v) | 122.5 | 128.5 |
Commencement Information
I3Sch. 13 Pt. 3 in force at 25.10.2019, see art. 1
Component | Work No. | Maximum length (m) | Maximum width (m) | Maximum height (m AGL) | Maximum height (m AOD) |
---|---|---|---|---|---|
Turbine hall building | 2A(ii) | 92 | 23 | 28 | 34 |
Heat recovery steam generator building (up to two) | 2A(iv) | 55 | 29 | 49 | 55 |
Exhaust gas emission flue stacks (up to two) | 2A(iv) | – | – | 123 | 129 |
Bypass stack (up to two) | 2A(v) | – | – | 123 | 129 |
Transformers | 2A(vi) | 36 | 20 | 11 | 17 |
Gas turbine air inlet filter house | 2A(vii) | 26 | 27 | 35 | 41 |
Power control centre | 2A(viii) | 17 | 17 | 6 | 12 |
Fuel gas station (up to two) | 2A(xv) | 26 | 19 | 7 | 13 |
Main pipe rack | 2B(i) | 1100 | 12 | 25 | 31 |
Battery storage facility including any structure (where constructed in two stages being stage 1 and stage 2) | 3B | 90 | 60 | 10 | 16 |
Gas insulated switchgear banking building or extension to 4A building | 4B | 18 | 12 | 11 | 17 |
Sludge lagoon (up to two) | 12B | 82 | 55 | – | – |
Cable Sealing End Compound | 8B(ii) | 35 | 28 | 20 | 26 |
Component | Work No. | Minimum height (m AGL) | Minimum height (m AOD) |
---|---|---|---|
Exhaust gas emission flue stack (up to two) | 2A(iv) | 122.5 | 128.5 |
Bypass stack (up to two) | 2A(v) | 122.5 | 128.5 |