The Southampton to London Pipeline Development Consent Order 2020

Application

71.—(1) For the protection of the statutory undertakers referred to in this Part of this Schedule the following provisions will, unless otherwise agreed in writing between the undertaker and the statutory undertaker concerned, have effect.

(2) Subject to sub-paragraph (3) or to the extent otherwise agreed in writing between the promoter and National Grid, where the benefit of this Order is transferred or granted to another person under article 8 (consent to transfer benefit of Order)—

(a)any agreement of the type mentioned in sub-paragraph (1) has effect as if it had been made between National Grid and the transferee or grantee (as the case may be); and

(b)written notice of the transfer or grant must be given to National Grid before or within 15 days of the date of that transfer or grant.

(3) Sub-paragraph (2) does not apply where the benefit of the Order is transferred or granted to National Grid (but see paragraph 81(3)(b)).