102.  Save for differences or disputes arising under paragraphs 98(5) and paragraph 95 any difference or dispute arising between the undertaker and SSE under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and SSE, be determined by arbitration in accordance with article 48 (arbitration).