The Lake Lothing (Lowestoft) Third Crossing Order 2020

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: SCHEDULE 1

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for the The Lake Lothing (Lowestoft) Third Crossing Order 2020, SCHEDULE 1. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Articles 2 and 4

SCHEDULE 1E+WAUTHORISED DEVELOPMENT

Commencement Information

I1Sch. 1 in force at 21.5.2020, see art. 1

In the administrative area of East Suffolk CouncilE+W

A development which, in accordance with a direction made by the Secretary of State for Transport on 22 March 2016 under section 35 of the 2008 Act, is development for which development consent is required, and associated development within the meaning of section 115(2) of the 2008 Act, comprising—

Work No. 1 – as shown on sheets 1 and 2 of the works plans and being the construction of new highway comprising—

(a)Work No. 1A

(i)the construction of new highway comprising carriageway and cycleway and forming the new bridge northern approach;

(ii)the construction of a new roundabout, together with related approach roads and adjacent cycleways;

(iii)the construction of earth embankments supporting the new highway;

(iv)the construction of a building to accommodate electrical plant and the installation of electrical apparatus; and

(v)associated landscaping.

(b)Work No. 1B

(i)the construction of new highway comprising carriageway and cycleway;

(ii)the construction of a bridge deck supporting the new highway;

(iii)the construction of an abutment and pier supporting the new bridge deck;

(iv)the construction of piles and pile caps supporting the abutment and pier; and

(v)the construction of new private means of access as shown on sheet 1 of the rights of way and access plans.

(c)Work No. 1C

(i)the construction of new highway comprising carriageway and cycleway;

(ii)the construction of a bridge deck supporting the new highway;

(iii)the construction of piers supporting the new bridge deck;

(iv)the construction of piles and pile caps supporting the piers; and

(v)the construction of new private means of access as shown on sheet 1 of the rights of way and access plans.

(d)Work No. 1D

(i)the construction of new highway comprising carriageway and cycleway;

(ii)the construction of a bridge deck supporting the new highway;

(iii)the construction of piers within the watercourse supporting the new bridge deck;

(iv)the construction of piles and pile caps within the watercourse supporting the piers and fendering;

(v)the construction of an opening section of bridge and associated barriers and signage; and

(vi)the construction of fendering within the watercourse.

(e)Work No. 1E

(i)the construction of new highway comprising carriageway and cycleway and forming the new bridge southern approach;

(ii)the construction of a bridge deck supporting the new highway;

(iii)the construction of abutments and piers supporting the new bridge deck;

(iv)the construction of piles and pile caps supporting the abutments and piers;

(v)the construction of earth embankment with retaining walls to support the new highway;

(vi)the construction of new private means of access as shown on sheet 2 of the rights of way and access plans; and

(vii)the improvement of existing highways, including realignment, to facilitate tie-ins to Work No. 2.

Work No. 2 – as shown on sheet 2 of the works plans and being the alteration of the existing highway comprising—

(a)the construction of a new roundabout, together with related approach roads and adjacent cycleways;

(b)the improvement of existing highways, including realignment, to facilitate tie-ins to the works referred to at paragraph (a) above and the construction of new private means of access to premises as shown on sheet 2 of the rights of way and access plans; and

(c)construction of new turning head on Durban Road and provision of adjacent cycleway.

Work No. 3 – as shown on sheet 1 of the works plans and comprising—

(a)the improvement of existing highways and the provision of new cycleways, including the realignment of existing highways to facilitate tie-ins to Work No. 1A; and

(b)the construction of new private means of access as shown on sheet 1 of the rights of way and access plans.

Work No. 4 – as shown on sheet 2 of the works plans and being the construction of new highway comprising carriageway and cycleway and including the construction of a new turning head, to provide access to existing premises including the construction of new private means of access to premises as shown on sheet 2 of the rights of way and access plans.

Work No. 5 – as shown on sheet 2 of the works plans and comprising—

(a)the construction of new highway comprising carriageway and cycleway to provide access to existing premises including the construction of new private means of access to premises as shown on sheet 2 of the rights of way and access plans; and

(b)the improvement of existing highways, including realignment, to facilitate tie-ins to the existing highway network and Work No.4 and the construction of new private means of access to premises as shown on sheet 2 of the rights of way and access plans.

Work No. 6 – as shown on sheet 2 of the works plans and being the construction of a new control tower building area for the new bridge comprising—

(a)the construction of a new control tower building for the operation of the lifting section of the new bridge;

(b)the construction of a new electrical substation and plant room; and

(c)the construction of new highway to provide a new access road and parking facilities for the new control tower building and electrical substation and plant room referred to in paragraphs (a) and (b), and to accommodate the new private means of access being as shown on sheet 2 of the rights of way and access plans.

Work No. 7 – as shown on sheet 2 of the works plans and being the construction of a new mooring within Lowestoft Harbour.

And for the purposes of or in connection with the construction of any of the works and other development mentioned above, ancillary or related development which does not give rise to any materially new or materially different effects than those assessed in the environmental statement, consisting of—

works within highways, including—

(a)alteration of the layout of any street permanently or temporarily, including increasing the width of the carriageway of any street by reducing the width of any kerb, footway, cycleway, or verge within the street; and altering the level or increasing the width of any such kerb, footway, cycleway or verge within the street, works for the strengthening, improvement, repair, maintenance or reconstruction of any street;

(b)street works, including breaking up or opening a street, or any sewer, drain or tunnel under it, and tunnelling or boring under a street;

(c)relocation or provision of new road traffic signs, signals, street lighting and carriageway lane markings; and

(d)works to place, alter, remove or maintain street furniture or apparatus (including statutory undertakers' apparatus) in, under or above a street, including mains, sewers, drains, pipes, cables, cofferdams, lights, fencing and other boundary treatments;

works within Lake Lothing (to the extent they are situated within the Order limits) to—

(e)alter, clean, modify, dismantle, refurbish, reconstruct, remove, relocate or replace any work or structure (including lake walls);

(f)carry out excavations and clearance, deepening, scouring, cleansing, dumping and pumping operations;

(g)carry out dredging, which may include such dredging works as may be required to provide side slopes or otherwise secure the dredged area against siltation, scouring or collapse;

(h)use, appropriate, sell, deposit or otherwise dispose of any materials (including liquids but excluding any wreck within the meaning of the Merchant Shipping Act 1995 M1) obtained in carrying out any such operations;

(i)remove and relocate any vessel or structure sunk, stranded, abandoned, moored or left (whether lawfully or not);

(j)temporarily remove, alter, strengthen, interfere with, occupy and use the banks, bed, foreshore, waters and walls of the lake;

(k)construct, place and maintain works and structures including piled fenders, protection piles and cofferdams; and

(l)provide lighting, signage and aids to navigation;

Marginal Citations

other works and development—

(m)for the strengthening, alteration or demolition of any building;

(n)to place, alter, divert, relocate, protect, remove or maintain services, plant and other apparatus and equipment belonging to statutory undertakers, utility companies and others in, under or above land, including mains, sewers, drains, pipes, cables, lights, cofferdams, fencing and other boundary treatments including bollards;

(o)ramps, steps, footpaths, footways, cycle tracks, cycleways, bridleways, equestrian tracks, non-motorised user routes or links, byways open to all traffic and crossing facilities;

(p)embankments, viaducts, bridges, aprons, abutments, shafts, foundations, retaining walls, drainage works, outfalls, pollution control devices, pumping stations, culverts, wing walls, fire suppression system water tanks and associated plant and equipment, highway lighting and fencing;

(q)settlement mitigation measures for the benefit or protection of, or in relation to, any land, building or structure, including monitoring and safeguarding of existing infrastructure, utilities and services affected by the authorised development;

(r)to alter the course of, or otherwise interfere with, navigable or non-navigable watercourses;

(s)landscaping, noise barriers, works associated with the provision of ecological mitigation, and other works to mitigate any adverse effects of the construction, operation or maintenance of the authorised development;

(t)areas of hard or soft landscaping works, or public realm, at various locations adjacent to the proposed highway and associated works;

(u)site preparation works, site clearance (including fencing and other boundary treatments, vegetation removal, works of demolition, including demolition of existing structures, and the creation of alternative highways or footpaths) and earthworks (including soil stripping and storage and site levelling);

(v)construction compounds and working sites, temporary structures, storage areas (including storage of spoil and other materials), temporary vehicle parking, construction fencing, perimeter enclosure, security fencing, construction-related buildings, welfare facilities, office facilities, other ancillary accommodation, construction lighting, haulage roads and other buildings, machinery, apparatus, works and conveniences;

(w)service compounds, plant and equipment rooms, offices, staff mess rooms, welfare facilities, and other ancillary and administrative accommodation;

(x)for the benefit or protection of the authorised development; and

(y)of whatever nature, as may be necessary or expedient for the purposes of, or for purposes associated with or ancillary to, the construction, operation or maintenance of the authorised development.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources