Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
10.—(1) The undertaker must not demolish the Woodside Farm House and associated structures (as identified on the map of heritage receptors) before the commencement of development at Development Zones A6, A5b or A7c as shown on development zone parameter plan.
(2) The Woodside Farm House and associated structures must not be demolished until they have been subject to a scheme of historic building recording by suitably qualified professionals and written confirmation obtained from the local planning authority that the works required under sub-paragraph (4)(a) to (c) have been completed and have been submitted to the local planning authority.
(3) The scheme of historic building recording must be undertaken in accordance with a written scheme of investigation which will be submitted to and approved in writing by the local planning authority before the recording begins. The written scheme of investigation must set out the level of recording required in accordance with the ‘Understanding Historic Buildings: A Guide to Good Recording Practice’ guidance prepared by Historic England (May 2016, or latest edition at the time the written scheme of investigation is prepared).
(4) The written scheme of investigation must include the following components—
(a)the identification, description and methodology for the level of recording necessary for the Woodside Farm House and associated structures as per the Historic England guidance referred to in sub-paragraph (3);
(b)research on the heritage asset necessary to understand their historical and architectural interest which is proportionate to the level of recording identified;
(c)an on-site survey of the Woodside Farm House and associated structures in accordance with paragraph (a) and to include photography; and
(d)completed research and analysis for presentation in an illustrated historic building recording report to be submitted within 12 weeks of recording work on site. The report will be suitable for deposition at an archival store as directed and approved by the local planning authority.
(5) The archive referred to in sub-paragraph (4)(d) should be collated, ordered and indexed in accordance with the requirements of the Management of Research Projects in the Historic Environment (MoRPHE) (Historic England, 2015).
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: